Legislation Details

File #: 26-1395    Version: 1 Name: Contract Amendment for Franklin Avenue/Green Street - York Rd to Runge Str. A1 (Increase) (Contract No. 2316-09171)
Type: Contract Amendment (Highway) Status: Agenda Ready
File created: 5/4/2026 In control: Administration, Bureau of
On agenda: 7/16/2026 Final action:
Title: PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS) Department(s): Transportation and Highways Vendor: K-Five Construction Corporation of Westmont, Illinois Request: Authorization for the Chief Procurement Officer to increase contract Good(s) or Service(s): Construction Services Location: Franklin Avenue/Green Street County Board District(s): 16 Original Contract Period: 1/30/2025 - 11/30/2028 Section: 21-FRAGS-00-PV Proposed Contract Period Extension: N/A Section: N/A Total Current Contract Amount Authority: $34,548,712.19 Original Board Approval: 2/6/2025: $34,548,712.19 Previous Board Increase(s) or Extension(s): N/A Previous Chief Procurement Officer Increase(s) or Extension(s): N/A Contract Utilization: The contract-specific goal set on this contract was zero. This Increase Requested: $975,140.71 Potential Fiscal Impact: FY 2026: $975,140.71 Accounts: Motor Fuel Tax: 11300.1500.29150.521536 ($351,983.42); Grant: 11900.1500.54...
Indexes: JENNIFER (SIS) KILLEN, Superintendent, Department of Transportation and Highways
Attachments: 1. 26-1395 Board Letter_Contract Amendment for Franklin Avenue Green Street_York Rd to Runge Str. A1 (Increase) (Contract No. 2316-09171; Section No. 21-FRAGS-00-PV)_BOARD, 2. 26-1395 Original Contract_Contract Amendment for Franklin Avenue Green Street_York Rd to Runge Str. A1 (Increase) (Contract No. 2316-09171; Section No. 21-FRAGS-00-PV)_BOARD
Date Ver.Action ByMotionResultAction DetailsMeeting DetailsVideo
No records to display.

title

PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS)

 

Department(s): Transportation and Highways

 

Vendor:  K-Five Construction Corporation of Westmont, Illinois

 

Request: Authorization for the Chief Procurement Officer to increase contract  

 

Good(s) or Service(s):  Construction Services

 

Location: Franklin Avenue/Green Street

 

County Board District(s): 16

 

Original Contract Period:  1/30/2025 - 11/30/2028  

 

Section: 21-FRAGS-00-PV

 

Proposed Contract Period Extension:  N/A  

 

Section: N/A

 

Total Current Contract Amount Authority:  $34,548,712.19

 

Original Board Approval:  2/6/2025: $34,548,712.19

 

Previous Board Increase(s) or Extension(s):  N/A

 

Previous Chief Procurement Officer Increase(s) or Extension(s):  N/A  

 

Contract Utilization: The contract-specific goal set on this contract was zero.

 

This Increase Requested:  $975,140.71  

 

Potential Fiscal Impact:  FY 2026: $975,140.71

 

Accounts:  Motor Fuel Tax: 11300.1500.29150.521536 ($351,983.42); Grant: 11900.1500.54179.521536 ($623,157.29)  

 

Contract Number(s):  2316-09171

 

IDOT Contract Number(s): N/A

 

Federal Project Number(s): ZAGE(365)

 

Federal Job Number(s): C-91-192-21

 

Summary:  The Department of Transportation and Highways respectfully requests the approval of the proposed amendment between the County and K-Five Construction Corporation, Westmont, Illinois.

 

On 2/6/2025, your Honorable Body awarded a contract to K-Five Construction Corporation, Westmont, Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.

 

The amendment accounts for changes associated with providing stone ramps for adjacent Tollway contract access, temporary pavement completion, Dominic Court lighting, removal of abandoned utilities, acceleration premium time costs, additional supervision costs, contract coordination with adjacent Illinois Tollway contracts, pavement maintenance, foundation removal, winter service and protection, railroad flaggers, sanitary sewer changes, protection of a sanitary force main, and barrier wall modifications.  These changes include additional work to the contract as well as adjustment to contract pay items.  All changes are germane to the contract and required to complete this project.

 

This contract was awarded pursuant to a publicly advertised Invitation for Bid (IFB) in accordance with the Cook County Procurement Code. K-Five Construction Corporation was the lowest, responsive, and responsible bidder.