File #: 24-4106    Version: 1 Name: Pagoda-CCI Joint Venture One, Elk Grove Village, Illinois
Type: Contract Amendment Status: Approved
File created: 7/10/2024 In control: Board of Commissioners
On agenda: 7/25/2024 Final action: 7/25/2024
Title: PROPOSED CONTRACT AMENDMENT Department(s): Department of Capital Planning and Policy Vendor: Pagoda-CCI Joint Venture One, Elk Grove Village, Illinois Request: Authorization for the Chief Procurement Officer to extend contract Good(s) or Service(s): DOC Division 1 & 1A Demolition Services Original Contract Period: 10/21/2019 - 6/7/2021 Proposed Amendment Type: Extension Proposed Contract Period: Extension period 7/5/2024 - 7/4/2025 Total Current Contract Amount Authority: $14,112,923.46 Original Approval (Board or Procurement): Board, 9/26/2019, $12,953,180.00 Increase Requested: N/A Previous Board Increase(s): 5/13/2021, $722,091.58; 12/14/2023, $423,930.32 Previous Chief Procurement Officer Increase(s): 7/25/2023, $13,721.56 Previous Board Renewals: N/A Previous Chief Procurement Officer Renewals: N/A Previous Board Extension(s): 5/13/2021, 6/8/2021 - 7/4/2022; 12/14/2023, 1/5/2024 - 7/4/2024 Previous Chief Procurement Officer Extension(s): ...
Indexes: EARL MANNING, Director, Office of Capital Planning and Policy

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Department of Capital Planning and Policy 

 

Vendor:  Pagoda-CCI Joint Venture One, Elk Grove Village, Illinois   

 

Request: Authorization for the Chief Procurement Officer to extend contract 

 

Good(s) or Service(s):  DOC Division 1 & 1A Demolition Services  

 

Original Contract Period: 10/21/2019 - 6/7/2021

 

Proposed Amendment Type: Extension

 

Proposed Contract Period:  Extension period 7/5/2024 - 7/4/2025 

 

Total Current Contract Amount Authority:  $14,112,923.46

 

Original Approval (Board or Procurement):  Board, 9/26/2019, $12,953,180.00

 

Increase Requested:  N/A

 

Previous Board Increase(s):  5/13/2021, $722,091.58; 12/14/2023, $423,930.32

 

Previous Chief Procurement Officer Increase(s): 7/25/2023, $13,721.56

 

Previous Board Renewals:  N/A

 

Previous Chief Procurement Officer Renewals:  N/A

 

Previous Board Extension(s): 5/13/2021, 6/8/2021 - 7/4/2022; 12/14/2023, 1/5/2024 - 7/4/2024

 

Previous Chief Procurement Officer Extension(s): 11/7/2022, 7/5/2022 - 7/4/2023; 7/25/2023, 7/5/2023 - 1/4/2024

 

Potential Fiscal Impact:  N/A

 

Accounts: N/A

 

Contract Number(s):  1885-17467

 

Concurrences:

The vendor has met the Minority- and Women-owned Business Enterprise Ordinance via: direct participation; The prime vendor is a certified MBE.

 

The Chief Procurement Officer concurs.

 

Summary:  This time-only extension is needed to allow the processing of MBE/WBE subcontractor invoices and to complete delayed backfill and grading work required under the base contract. It is also needed to allow the Pagoda-CCI Joint Venture to complete work in the judges’ parking lot area. That repaving is delayed because of the unforeseen need for environmental work, being executed by another vendor, to remove and remediate around an underground storage tank.

 

This contract is awarded through a publicly advertised Invitation for Bid (IFB) in accordance with Cook County Procurement Code.  Competitive bidding procedures were followed in accordance with the Cook County Procurement Code.  Bids were solicited for the services.  The Pagoda-CCI Joint Venture was the lowest, responsive and responsible bidder.  

end