title
PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS)
Department(s): Transportation and Highways
Vendor: Acura, Inc, Bensenville, Illinois
Action: Refer to Transportation Committee
Request: Authorization for the Chief Procurement Officer to increase contract
Good(s) or Service(s): Construction Services
Location: Curb Ramp Improvement Program 2022 North
County Board District(s): 12, 14, and 15
Original Contract Period: 7/14/2023 - 1/1/2028
Section: 23-CRIPN-00-CG
Proposed Contract Period Extension: N/A
Section: N/A
Total Current Contract Amount Authority: $939,796.00
Original Board Approval: 6/29/2023, $939,796.00
Previous Board Increase(s) or Extension(s): N/A
Previous Chief Procurement Officer Increase(s) or Extension(s): N/A
This Increase Requested: $320,514.44
Potential Fiscal Impact: FY 2024 $320,514.44
Accounts: Motor Fuel Tax: 11300.1500.29150.521536
Contract Number(s): 2311-02230
IDOT Contract Number(s): N/A
Federal Project Number(s): N/A
Federal Job Number(s): N/A
Concurrences:
The vendor has met the Minority- and Women-owned Business Enterprise Ordinance via: Direct participation. The prime vendor is a certified MBE.
The Chief Procurement Officer concurs.
Summary: The Department of Transportation and Highways respectfully requests approval of the proposed Amendment between the County and Acura, Inc, Bensenville, Illinois.
This contract was approved by the Cook County Board on June 29, 2023, for Curb Ramp Improvement Program 2022 North located within the Cook County Board Districts 12, 14, and 15 in accordance with the plans and specifications. The amendment accounts for changes associated with excavation for ADA ramps, adjacent sidewalk installation to ADA ramps, soils testing and disposal. Additional excavation was required to comply with ADA requirements and soils testing determined more spoils needed to be disposed of as Non-Special Waste than originally anticipated in the design phase.
Finally, the amendment accounts for work that was not included in the project but required to meet the goals of the project includes installation of a segmental block wall to allow for meeting ADA requirements for locations with exceeding allowable elevation differences based on existing field conditions.
This contract was awarded pursuant to a publicly advertised Invitation for Bid (IFB) in accordance with the Cook County Procurement Code. Acura, Inc. was the lowest, responsive, and responsible bidder.