File #: 25-2993    Version: 1 Name: Contract Amendment for County Line Road – Sauk Trail Road – Western Ave. to Ashland Ave. A2 Increase and Extension Contract no. 2038-18488D
Type: Contract Amendment (Highway) Status: Held / Deferred in Committee
File created: 5/27/2025 In control: Transportation Committee
On agenda: 7/24/2025 Final action:
Title: PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS) Department(s): Transportation and Highways Vendor: Christopher B. Burke Engineering, Ltd., Rosemont, Illinois Request: Authorization for the Chief Procurement Officer to extend and increase contract Good(s) or Service(s): Preliminary Engineering Services Location: Unincorporated Bloom Township County Board District(s): 5, 6 Original Contract Period: 10/1/2022 - 9/30/2024 Section: 21-C1131-00-PV Proposed Contract Period Extension: 10/1/2025 - 9/30/2026 Section: N/A Total Current Contract Amount Authority: $1,130,726.00 Original Board Approval: 9/22/2022, $1,130,726.00 Previous Board Increase(s) or Extension(s): N/A Previous Chief Procurement Officer Increase(s) or Extension(s): 11/26/2024, (10/1/2024 - 9/30/2025) Contract Utilization: The vendor has met the Minority- and Women-owned Business Enterprise Ordinance via: Direct participation. This Increase Requested: $271,699.00 Pot...
Indexes: JENNIFER (SIS) KILLEN, Superintendent, Department of Transportation and Highways

title

PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS)

 

Department(s): Transportation and Highways

 

Vendor:  Christopher B. Burke Engineering, Ltd., Rosemont, Illinois  

 

Request: Authorization for the Chief Procurement Officer to extend and increase contract  

 

Good(s) or Service(s):  Preliminary Engineering Services  

 

Location: Unincorporated Bloom Township

 

County Board District(s): 5, 6

 

Original Contract Period:  10/1/2022 - 9/30/2024  

 

Section: 21-C1131-00-PV

 

Proposed Contract Period Extension:  10/1/2025 - 9/30/2026 

 

Section:  N/A

 

Total Current Contract Amount Authority:  $1,130,726.00

 

Original Board Approval:  9/22/2022, $1,130,726.00

 

Previous Board Increase(s) or Extension(s):  N/A

 

Previous Chief Procurement Officer Increase(s) or Extension(s):  11/26/2024, (10/1/2024 - 9/30/2025)  

 

Contract Utilization: The vendor has met the Minority- and Women-owned Business Enterprise Ordinance via: Direct participation.

 

This Increase Requested:  $271,699.00  

 

Potential Fiscal Impact:  FY 2026 $271,699.00

 

Accounts:  Rebuild Illinois Bond: 11300.1500.29152.560019 

 

Contract Number(s):  2038-18488D

 

IDOT Contract Number(s): N/A

 

Federal Project Number(s): N/A

 

Federal Job Number(s): N/A

 

Summary:  The Department of Transportation and Highways respectfully requests approval of the proposed Contract Amendment 2 between the County and Christopher B. Burke Engineering, Ltd., Rosemont, Illinois.

 

This contract provides for the preparation of preliminary engineering environmental (Phase I) study for the reconstruction of Sauk Trail from Western Avenue to Ashland Avenue, including reconstruction of the bridge structure over Thorn Creek. The improvements will enable the Department to protect the public investment in the highway system and provide a safe and sustainable highway in accordance with the Department’s mission statement.

 

This amendment is needed to support additional tasks identified during the Phase I study that are needed to complete the study and better meet the project goals. These additional tasks include extending the eastern limit of the project by approximately 1,500' to allow the proposed shared-use path to connect in with an existing sidewalk system, designing additional improvements at the intersection of Sauk Trail and Western Avenue, and updating the Phase I documentation to keep the project eligible for federal funding in the future.

 

This contract is awarded pursuant to a publicly advertised Request for Qualifications (RFQ) in accordance with Cook County Procurement Code. Christopher B. Burke Engineering, Ltd. was selected based on established evaluation criteria.

end