PROPOSED PAYMENT APPROVAL
Department(s): Department of Transportation and Highways
Action: Payment Approval
Payee: Western Remac, Inc.
Good(s) or Service(s): Construction Services
Fiscal Impact: FY 2023 $32,837.31
Accounts: 11300.1500.29150.540370
Contract Number(s): 1885-17684
Summary: The Department of Transportation and Highways (DOTH) respectfully submits the approval of a single payment to Western Remac Inc. for the contract retention as result of successful completion of the contracted work. All work was completed within the contract period 04/01/2019 - 03/31/2022, and the contract quantities have been agreed to and finalized for contract close out. DOTH is requesting County Board approval to pay the final invoice in the amount of $32,837.31. The contract expired before the invoice could be paid.