File #: 19-5311    Version: 1 Name: Gallagher Asphalt Corporation, Thornton, Illinois Contract Amendment for PPRP South
Type: Contract Amendment (Highway) Status: Approved
File created: 8/26/2019 In control: Board of Commissioners
On agenda: 9/26/2019 Final action: 9/26/2019
Title: PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS) Department(s): Transportation and Highways Vendor: Gallagher Asphalt Corporation, Thornton, Illinois Request: Authorization for the Chief Procurement Officer to Increase the contract Good(s) or Service(s): Construction Services Location: Pavement Reservation and Rehabilitation Program - South 2019 Sauk Trail from Governors Highway to West of Lakewood Boulevard Kedzie Avenue from County Air Drive to 147th Street Stony Island Avenue from Joe Orr Road to Glenwood Lansing Road Harlem Avenue from Steger Road to Laraway Road / Sauk Trial County Board District(s): 5 & 6 Original Contract Period: 5/2/2019 - 11/27/2022 Section: 19-PPRPS-00-PV Proposed Contract Period Extension: N/A Section: N/A Total Current Contract Amount Authority: $2,651,829.08 Original Board Approval: 4/25/2019, $2,651,829.08 Previous Board Increase(s) or Extension(s): N/A Previous Chief Procurement Officer Increase(s) or Ex...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS)

Department(s): Transportation and Highways

Vendor: Gallagher Asphalt Corporation, Thornton, Illinois

Request: Authorization for the Chief Procurement Officer to Increase the contract

Good(s) or Service(s): Construction Services

Location:
Pavement Reservation and Rehabilitation Program - South 2019
Sauk Trail from Governors Highway to West of Lakewood Boulevard
Kedzie Avenue from County Air Drive to 147th Street
Stony Island Avenue from Joe Orr Road to Glenwood Lansing Road
Harlem Avenue from Steger Road to Laraway Road / Sauk Trial

County Board District(s): 5 & 6

Original Contract Period: 5/2/2019 - 11/27/2022

Section: 19-PPRPS-00-PV

Proposed Contract Period Extension: N/A

Section: N/A

Total Current Contract Amount Authority: $2,651,829.08

Original Board Approval: 4/25/2019, $2,651,829.08

Previous Board Increase(s) or Extension(s): N/A

Previous Chief Procurement Officer Increase(s) or Extension(s): N/A

This Increase Requested: $485,974.16

Potential Fiscal Impact: FY 2019 $485,974.16

Accounts: Motor Fuel Tax: 11300.1500.29150.560019

Contract Number(s): 1955-17738

IDOT Contract Number(s): "N/A"

Federal Project Number(s): "N/A"

Federal Job Number(s): "N/A"

Concurrences:
The vendor has met the Minority- and Women-owned Business Enterprise Ordinance via direct participation and partial WBE waiver.

The Chief Procurement Officer Concurs.

Summary: The quantities as shown on the contract documents were estimated for bidding purposes only. This change represents the difference between the estimated quantities and actual field quantities of work performed with additional quantities required for asphalt pavement items, combination curb and gutter items, pavement patching items, mixture for cracks, drainage items, and earth excavation.

New items were added for Class B patches, recessed reflective pavement markers, welded wire reinforcement, ag...