title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Sumit Construction Co., Inc., Chicago, Illinois
Action: Completion of Construction Approval Resolution
Good(s) or Service(s): Construction Services
Location of Project:
Ridgeland Avenue - Bus Route 384 - Bus Pads
108th Street to 88th Street
Section: 17-IICTR-01-RP
County Board District: 6
Contract Number: 1999-17920
Federal Project Number: N/A
Federal Job Number: N/A
Final Cost: $128,767.06
Account String: Motor Fuel Tax: 11300.1500.29150.521536
Percent Above or Below Construction Contract Bid Amount: -$12,448.94 or 8.8% below the Construction Contract Bid Amount
Summary: The Department of Transportation and Highways respectfully requests approval of the proposed Completion of Construction for work done on Ridgeland Avenue. The proposed improvement consisted of PACE bus stop improvements including PCC pads, ADA ramps and landings, and any collateral and auxiliary work as needed to complete the project.
The decreases are attributed to the difference between the estimated quantities and actual field quantities of work performed with less quantities required for tree root pruning, earth excavation, and on-site monitoring of regulated substances.