File #: 18-4777    Version: 1 Name: M.Q. Construction, Chicago, Illinois
Type: Completion of Construction Approval Resolution (Highway) Status: Approved
File created: 7/10/2018 In control: Board of Commissioners
On agenda: 9/12/2018 Final action: 9/12/2018
Title: PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): M.Q. Construction, Chicago, Illinois Action: Approval of Proposed Completion of Construction Approval Resolution Good(s) or Service(s): Construction Services - JOC Location of Project: Crawford Avenue- Oakton Street to Golf Road, in the Village of Skokie Section: 18-W4339-00-PV County Board District: 13 Contract Number: 1555-14475-SWSBE18 Federal Project Number: N/A Federal Job Number: N/A Final Cost: $175,262.66 Percent Above or Below Construction Contract Bid Amount: $161,134.00 or 47.9% below the Construction Contract Bid Amount Summary: The Department of Transportation and Highways respectfully requests approval of the Proposed Completion of Construction Services. The improvements consisted of milling and resurfacing of the existing bituminous pavement patches with hot-mix asphalt, drainage repairs and adju...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways

title

PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)

 

Department: Transportation and Highways

 

Other Part(ies):  M.Q. Construction, Chicago, Illinois

 

Action:  Approval of Proposed Completion of Construction Approval Resolution

 

Good(s) or Service(s):  Construction Services - JOC

 

Location of Project:  Crawford Avenue- Oakton Street to Golf Road, in the Village of Skokie

 

Section:  18-W4339-00-PV

 

County Board District:  13

 

Contract Number:   1555-14475-SWSBE18

 

Federal Project Number:   N/A  

 

Federal Job Number:   N/A

 

Final Cost:  $175,262.66

 

Percent Above or Below Construction Contract Bid Amount:  $161,134.00 or 47.9% below the Construction Contract Bid Amount

 

Summary:  The Department of Transportation and Highways respectfully requests approval of the Proposed Completion of Construction Services.  The improvements consisted of milling and resurfacing of the existing bituminous pavement patches with hot-mix asphalt, drainage repairs and adjustments, traffic control and protection, pavement marking and other related work to complete the project.

 

The final project cost is $161,134.00 or 47.9% below the Construction Contract Bid Amount.  The decreases are attributed to the difference between the estimated quantities and actual field quantities of work performed with decrease in asphalt, pavement patching, storm sewer and striping items per field conditions.