File #: 19-5638    Version: 1 Name: 156th Street, Commercial Avenue. to Halsted Street, City of Harvey, Illinois
Type: Completion of Construction Approval Resolution (Highway) Status: Approved
File created: 9/17/2019 In control: Board of Commissioners
On agenda: 10/24/2019 Final action: 10/24/2019
Title: PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): Capitol Cement Company, Chicago, Illinois Action: Approval of the Completion of Construction Resolution Good(s) or Service(s): Construction and Construction Engineering Location of Project: 156th Street- Commercial Ave. to Halsted St. Section: 14-15632-01-FP County Board District: 5 Contract Number: 1685-15592 Federal Project Number: DR-IN-R3-01 Federal Job Number: C-91-184-15 Final Cost: $1,304,436.98 Account: CDBG: 11900.1500.50685.521536 EDP: 11900.1500.53439.521536 Percent Above or Below Construction Contract Bid Amount: $76,753.88 or 6.25% above the Construction Engineering Contract Amount. Summary: The Department of Transportation and Highways respectfully requests approval of the Proposed Completion of Construction Resolution for work done by Capitol Cement Chicago, Illinois. The proposed improvement consisting...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways

title

PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)

 

Department: Transportation and Highways

 

Other Part(ies):  Capitol Cement Company, Chicago, Illinois

 

Action:  Approval of the Completion of Construction Resolution

 

Good(s) or Service(s):  Construction and Construction Engineering

 

Location of Project:  156th Street- Commercial Ave. to Halsted St.

 

Section:  14-15632-01-FP

 

County Board District:  5

 

Contract Number:  1685-15592

 

Federal Project Number:  DR-IN-R3-01

 

Federal Job Number:  C-91-184-15

 

Final Cost:  $1,304,436.98

 

Account:

CDBG: 11900.1500.50685.521536

EDP: 11900.1500.53439.521536

 

Percent Above or Below Construction Contract Bid Amount:  $76,753.88 or 6.25% above the Construction Engineering Contract Amount.

 

Summary:   The Department of Transportation and Highways respectfully requests approval of the Proposed Completion of Construction Resolution for work done by Capitol Cement Chicago, Illinois. The proposed improvement consisting of reconstruction of the existing two lane roadway to a 24 feet wide concrete pavement with aggregate subgrade, combination concrete curb and gutter, storm sewer/combination sewer, parkway catch basins, cast-in-place pipe lining, signing, landscaping with topsoil, seeding and traffic control and protection and any collateral and auxiliary work as needed to complete the project. The increases are attributed to the difference between the estimated quantities and actual field quantities of work performed with increase in earth excavation, bituminous related items, storm sewer related items and scale pit removal.

 

 

end