title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Capitol Cement Company, Inc. of Chicago, Illinois
Action: Approval of the Completion of Construction Resolution
Good(s) or Service(s): Construction and Construction Engineering
Location of Project: Center Street, 171st Street to 159th Street, City of Harvey, Illinois
Section: 02-W5208-02-RP
County Board District: 5
Contract Number: 1555-14616
Federal Project Number: M-4003-(379)
Federal Job Number: C-91-424-14
Final Cost: $9,671,667.26
Accounts:
MFT: 11300.1500.29150.560019
STU: 11900.1500.51135.560019
TARP: 11900.1500.51140.560019
CDBG: 11900.1500.50685.560019
Percent Above or Below Construction Contract Bid Amount: $183,956.19 or 1.94% above the Construction Contract Bid Amount
Summary: The Department of Transportation and Highways respectfully submits for approval the Proposed Completion of Construction for work done by Capitol Cement Company, Inc., Chicago, Illinois. The proposed improvement consisted of reconstruction of existing composite pavement to 12 inch concrete pavement along with a 12 inch aggregate subgrade, combination curb and gutter, storm sewer, traffic signal improvement, temporary traffic signals, water main installation, pavement markings, signing, parkway landscaping with topsoil, seeding, detour routing, traffic protection and any collateral and auxiliary work as needed to complete the project. The increases are attributed to the difference between the estimated quantities and actual field quantities of work performed with addition in earth excavation, portland concrete cement driveway pavement, non-special waste disposal, trench backfill and drainage items per field conditions.