File #: 23-5219    Version: 1 Name: Agreement with (UIGA) for HSIP Package #1 (23-HSIP1-00-TL)
Type: Agreement (Highway) Status: Approved
File created: 10/3/2023 In control: Board of Commissioners
On agenda: 11/16/2023 Final action: 11/16/2023
Title: PROPOSED AGREEMENT (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): Illinois Department of Transportation (IDOT) Request: Approval of proposed Joint Funding Agreement for Construction Work Goods or Services: Construction and Construction Engineering Location: City of Oak Forest; City of Blue Island; Village of Hazel Crest, Illinois Section Number: 23-HSIP1-00-TL County Board District: 5, 6 Centerline Mileage: N/A Agreement Period: One-time agreement Agreement Number(s): N/A Fiscal Impact: $4,800,818.40 ($982,962.00 to be reimbursed from the Federal Highway Administration (FHWA)) Accounts: 11300.1500.29152.560019 ($3,817,856.40); 11900.1500.54354.560019 ($982,962.00) Summary: The Department of Transportation and Highways respectfully requests approval of the proposed Agreement between the County and the Illinois Department of Transportation (IDOT). The County will be the lead agency for construction an...
Indexes: JENNIFER (SIS) KILLEN, Superintendent, Department of Transportation and Highways

title

PROPOSED AGREEMENT (TRANSPORTATION AND HIGHWAYS)

 

Department:  Transportation and Highways

 

Other Part(ies):  Illinois Department of Transportation (IDOT) 

 

Request:   Approval of proposed Joint Funding Agreement for Construction Work 

 

Goods or Services:  Construction and Construction Engineering

 

Location:   City of Oak Forest; City of Blue Island; Village of Hazel Crest, Illinois 

 

Section Number:  23-HSIP1-00-TL

 

County Board District:  5, 6 

 

Centerline Mileage:  N/A

 

Agreement Period:  One-time agreement 

 

Agreement Number(s):  N/A

 

Fiscal Impact:   $4,800,818.40 ($982,962.00 to be reimbursed from the Federal Highway Administration (FHWA))

 

Accounts:   11300.1500.29152.560019 ($3,817,856.40); 11900.1500.54354.560019 ($982,962.00)

 

Summary:   The Department of Transportation and Highways respectfully requests approval of the proposed Agreement between the County and the Illinois Department of Transportation (IDOT). The County will be the lead agency for construction and construction engineering of traffic signal replacement along Ridgeland Avenue at 143rd Street, Kedzie Avenue at 139th Street and Kedzie Avenue at 175th Street. The FHWA will pay up to a maximum of $982,962.00 toward the project construction and construction engineering costs and, per the terms of the agreement, Cook County will be responsible for the remaining balance of construction and construction engineering costs, estimated at $3,817,856.40. 

end