title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): K-Five Construction Corporation, Westmont, Illinois
Action: Completion of Construction Approval Resolution
Good(s) or Service(s): Construction Services
Location of Project: Roberts Road - Valley Drive to 87th Street
Section: 19-W3216-00-PV
County Board District: 6, 17
Contract Number: 2028-18123
Federal Project Number: N/A
Federal Job Number: N/A
Final Cost: $7,471,684.77
Percent Above or Below Construction Contract Bid Amount: 0%
Summary: The Department of Transportation and Highways respectfully requests approval of the proposed completion of construction resolution for work done in Cook County Board Districts six and seventeen. The Roberts Road improvements include concrete pavement, hot-mixed asphalt, pavement patching, curb and gutter replacement, median removal, restriping, ADA ramp improvements, signal modernization with interconnect, and all other work as required to complete the improvement.
The amended awarded contract amount of this project was $7,471,684.77 and the final construction cost of the contract is $7,471,684.77. This resolution is required as part of the documentation and certification of the completion of construction activities by the Department to the funding Agency, IDOT.
end