File #: 26-1396    Version: 1 Name: Contract Amendment for 88th Street – Cork Avenue at I-294 Interchange A1 (Increase) (Contract No. 2316-10041)
Type: Contract Amendment (Highway) Status: Agenda Ready
File created: 5/4/2026 In control: Administration, Bureau of
On agenda: 6/11/2026 Final action:
Title: PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS) Department(s): Transportation and Highways Vendor: K-Five Construction Corporation, Westmont, Illinois Request: Authorization for the Chief Procurement Officer to increase contract Good(s) or Service(s): Construction Services Location: 88th/Cork Avenue at I-294 Interchange County Board District(s): 6 Original Contract Period: 6/27/2024 - 7/20/2029 Section: 19-W3019-00-PV Proposed Contract Period Extension: N/A Section: N/A Total Current Contract Amount Authority: $25,819,361.29 Original Board Approval: 6/13/2024: $25,819,361.29 Previous Board Increase(s) or Extension(s): N/A Previous Chief Procurement Officer Increase(s) or Extension(s): N/A Contract Utilization: The Contract-Specific goal set on this contract is Zero. This Increase Requested: $2,042,906.28 Potential Fiscal Impact: FY 2026: $2,042,906.28 Accounts: Motor Fuel Tax: 11300.1500.29150.560019: $479,294.09; 11300.1500.29...
Indexes: JENNIFER (SIS) KILLEN, Superintendent, Department of Transportation and Highways
Date Ver.Action ByMotionResultAction DetailsMeeting DetailsVideo
No records to display.
title
PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS)

Department(s): Transportation and Highways

Vendor: K-Five Construction Corporation, Westmont, Illinois

Request: Authorization for the Chief Procurement Officer to increase contract

Good(s) or Service(s): Construction Services

Location: 88th/Cork Avenue at I-294 Interchange

County Board District(s): 6

Original Contract Period: 6/27/2024 - 7/20/2029

Section: 19-W3019-00-PV

Proposed Contract Period Extension: N/A

Section: N/A

Total Current Contract Amount Authority: $25,819,361.29

Original Board Approval: 6/13/2024: $25,819,361.29

Previous Board Increase(s) or Extension(s): N/A

Previous Chief Procurement Officer Increase(s) or Extension(s): N/A

Contract Utilization: The Contract-Specific goal set on this contract is Zero.

This Increase Requested: $2,042,906.28

Potential Fiscal Impact: FY 2026: $2,042,906.28

Accounts: Motor Fuel Tax: 11300.1500.29150.560019: $479,294.09; 11300.1500.29150.521536: $1,563,612.19

Contract Number(s): 2316-10041

IDOT Contract Number(s): N/A

Federal Project Number(s): 284E(761)

Federal Job Number(s): C-91-008-20

Summary: The Department of Transportation and Highways respectfully requests the approval of the proposed amendment between Cook County and K-Five Construction Corporation of Westmont, Illinois.

On 6/13/2024, your Honorable Body awarded a contract to K-Five Construction Corporation, Westmont, Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.

The amendment accounts for changes required from unexpected field conditions, design changes, and coordination with adjacent projects. The project components also needed to be closely coordinated with the adjacent Illinois Tollway's I-294 widening project. The sequence of both projects required close coordination, initially with the 88th / Cork project needing to start after the Tollway project on the 88th Bridge. Ne...

Click here for full text