title
PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Project Type: Motor Fuel Tax Project Supplemental Improvement Resolution
Request: Refer to the Committee of Roads and Bridges
Project: Pavement Rehabilitation 2014
Location: Various Locations throughout Cook County
Section: 14-REHAB-01-PV
County Board District: Countywide
Centerline Mileage: N/A
Fiscal Impact: $600,000.00
Accounts: Motor Fuel Tax Fund: 600-585 Account
Board Approved Date and Amount: 05-21-2014 $2,750,000.00
Increased Amount: $600,000.00
Total Adjusted Amount: $3,350,000.00
Summary: The Department of Transportation and Highways respectfully submits for adoption a supplemental resolution appropriating funds for the improvement of County Highways at various locations throughout Cook County. This improvement, as proposed, will consist of milling and resurfacing of the existing bituminous pavement with hot-mix asphalt or diamond grinding existing concrete pavement and shall include patching, concrete pavement replacement, drainage repairs and adjustments, sidewalk removal and ADA compliant ramp replacement, traffic control and protection, pavement marking, landscaping, engineering and other necessary highway appurtenances.
This improvement will rehabilitate various severely deteriorated roadway segments which suffered from the unusually harsh winter weather and is needed to protect the public investment in the highway system and provide safe, efficient and sustainable highways.
On 5/21/2014, your Honorable Body approved an Improvement Resolution appropriating $2,750,000.00 towards completion of this improvement. Additional funding is required to cover the cost of work as bid. In order to complete work at two of three priority locations this year, a change in construction material, from Hot Mix Asphalt to Portland Cement Concrete was approved by the De...