File #: 18-4767    Version: 1 Name: Change in Plans Pavement Marking_Various_Preform Traffic Control System, Ltd. 12-90-094
Type: Change in Plans and Extra Work (Highway) Status: Approved
File created: 7/10/2018 In control: Roads and Bridges Committee (Inactive. There is now a Transportation Committee)
On agenda: 7/25/2018 Final action: 9/12/2018
Title: PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): Preformed Traffic Control Systems, Ltd., Elk Grove Village, Illinois Action: Refer to Roads and Bridges Committee - Proposed Change in Plans and Extra Work Section: 12-8PVMK-35-GM, 14-8PVMK-36-GM, 15-8PVMK-37-GM, 16-8PVMK-01-GM Contract Number(s): 12-90-094 IDOT Contract Number(s): N/A Federal Project Number(s): N/A Federal Job Number(s): N/A Location: Countywide Board District: Countywide Good(s) or Service(s): Pavement Marking Services Fiscal Impact: $1,060,278.76 (decrease) Accounts: 11300.1500.29150.540370 Summary: The Department of Transportation and Highways respectfully submits a change in plans and extra work on the above captioned project. On July 10, 2012, your honorable Body awarded a contract to Preform Traffic Control System, Ltd., Elk Grove Village, Illinois for the aforesaid improvement to be completed in accordan...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways

title

PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)

 

Department: Transportation and Highways

 

Other Part(ies):  Preformed Traffic Control Systems, Ltd., Elk Grove Village, Illinois 

 

Action:  Refer to Roads and Bridges Committee - Proposed Change in Plans and Extra Work

 

Section:  12-8PVMK-35-GM, 14-8PVMK-36-GM, 15-8PVMK-37-GM, 16-8PVMK-01-GM

 

Contract Number(s): 12-90-094

 

IDOT Contract Number(s): N/A

 

Federal Project Number(s): N/A

 

Federal Job Number(s): N/A

 

Location:  Countywide

 

Board District:  Countywide

 

Good(s) or Service(s):  Pavement Marking Services 

 

Fiscal Impact:  $1,060,278.76 (decrease) 

 

Accounts:  11300.1500.29150.540370

 

Summary:  The Department of Transportation and Highways respectfully submits a change in plans and extra work on the above captioned project.

 

On July 10, 2012, your honorable Body awarded a contract to Preform Traffic Control System, Ltd., Elk Grove Village, Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.

 

The quantities as shown on the contract documents were estimated for bidding purposes only.  This change represents the difference between the estimated quantities and actual field quantities of work performed with savings due to less quantities required to maintain pavement markings.

end