title
PROPOSED CONTRACT AMENDMENT
 
Department(s):  Department of Facilities Management  
 
Vendor:  Columbia Pipe and Supply, Chicago, Illinois  
 
Request: Authorization for the Chief Procurement Officer to increase contract  
 
Good(s) or Service(s):  Sloan Plumbing Parts  
 
Original Contract Period: 11/15/2019 - 11/14/2022, with one (1), one (1) year renewal option
 
Proposed Amendment Type:  Increase
 
Proposed Contract Period:  N/A   
 
Total Current Contract Amount Authority:  $103,600.00 
 
Original Approval (Board or Procurement):   Procurement, 11/8/2019, $103,600.00
 
Increase Requested:  $100,000.00 
 
Previous Board Increase(s):   N/A 
 
Previous Chief Procurement Officer Increase(s): N/A 
 
Previous Board Renewals:  N/A 
 
Previous Chief Procurement Officer Renewals:  N/A 
 
Previous Board Extension(s): N/A 
 
Previous Chief Procurement Officer Extension(s): N/A
 
Potential Fiscal Impact:  FY 2021 $24,999.00, FY2022 $75,001.00
 
Accounts: 11100.1200.12355.530188 
 
Contract Number(s):  1945-17991
 
Concurrences:
The contract-specific goal set on this contract was zero.
 
The Chief Procurement Officer concurs.
 
Summary:   This increase will allow the Department of Facilities Management to continue to receive Sloan Plumbing parts at various Cook County Facilities. 
 
This contract was awarded through a publicly advertised competitive bidding process in accordance with the Cook County Procurement Code.  Columbia Pipe and Supply Company was the lowest, responsive and responsible bidder.   
   