File #: 17-1239    Version: 1 Name: Prime Electric Company, Inc., Chicago, Illinois
Type: Contract Status: Approved
File created: 1/18/2017 In control: Board of Commissioners
On agenda: 2/8/2017 Final action: 2/8/2017
Title: PROPOSED CONTRACT Department(s): Facilities Management Vendor: Prime Electric Company, Inc., Chicago, Illinois Request: Authorization for the Chief Procurement Officer to enter into and execute Good(s) or Service(s): Switchgear Preventative Maintenance, Repair and Replacement of Electrical Distribution Equipment Contract Value: $2,056,256.00 Contract period: 3/1/2017 - 2/28/2020, with two (2), one (1) year renewal options Potential Fiscal Year Budget Impact: FY 2017 $514,063.98, FY 2018 $685,418.84, FY2019 $685,418.64, FY 2020 $171,354.74 Accounts: 200-450 Maintenance of Plant Equipment Contract Number(s): 1545-15104 Concurrences: The vendor has met the Minority- and Women- owned Business Enterprise Ordinance via direct participation. The Chief Procurement Officer concurs. Summary: The Department of Facilities Management request authorization for the Chief Procurement Officer to enter into and execute a contract with Prime Electric Company, Inc. for repair, m...
Indexes: BILQIS JACOBS-EL, Director, Department of Facilities Management

title

PROPOSED CONTRACT

 

Department(s):  Facilities Management

 

Vendor:  Prime Electric Company, Inc., Chicago, Illinois

 

Request: Authorization for the Chief Procurement Officer to enter into and execute

 

Good(s) or Service(s): Switchgear Preventative Maintenance, Repair and Replacement of Electrical Distribution Equipment

 

Contract Value:  $2,056,256.00

 

Contract period:  3/1/2017 - 2/28/2020, with two (2), one (1) year renewal options 

 

Potential Fiscal Year Budget Impact: FY 2017 $514,063.98, FY 2018 $685,418.84, FY2019 $685,418.64, FY 2020 $171,354.74

 

Accounts:  200-450 Maintenance of Plant Equipment

 

Contract Number(s):  1545-15104 

 

Concurrences:

The vendor has met the Minority- and Women- owned Business Enterprise Ordinance via direct participation.

 

The Chief Procurement Officer concurs.

 

Summary: The Department of Facilities Management request authorization for the Chief Procurement Officer to enter into and execute a contract with Prime Electric Company, Inc. for repair, maintenance and replacement of high voltage electrical power systems.  This contract will ensure electrical disconnect switches, fuses and circuit breakers used to control, protect and isolate electrical equipment are operational.

 

This contract is awarded through the competitive bidding process in accordance with the Cook County Procurement Code.  Prime Electric Company, Inc. was the lowest, responsive and responsible bidder.

end