File #: 14-5864    Version: 1 Name: Record 5864 88th C in P
Type: Change in Plans and Extra Work (Highway) Status: Approved
File created: 10/6/2014 In control: Board of Commissioners
On agenda: 11/19/2014 Final action: 11/19/2014
Title: PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): K-Five Construction Corporation, Lemont, Illinois Action: Refer to the Committee of Roads and Bridges Section: 03-W3017-03-FP Contract Number(s): N/A IDOT Contract Number(s): N/A Federal Project Number(s): N/A Federal Job Number(s): N/A Location: 88th Avenue, 103rd Street to 87th Street in the Cities of Palos Hills and Hickory Hills Board District: 17 Good(s) or Service(s): Adjustment of Quantities and New Items Fiscal Impact: $173,169.46 decrease Accounts: Motor Fuel Tax Fund Account 600-600 Summary: The Department of Transportation and Highways respectfully submits a change in plans and extra work on the above captioned project in the Cities of Palos Hills and Hickory Hills. On 7/12/2011, your honorable Body awarded a contract to K-Five Construction Corporation, Lemont, Illinois for the aforesaid im...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)
 
Department: Transportation and Highways
 
Other Part(ies):  K-Five Construction Corporation, Lemont, Illinois  
 
Action:  Refer to the Committee of Roads and Bridges
 
Section:  03-W3017-03-FP
 
Contract Number(s): N/A
 
IDOT Contract Number(s): N/A
 
Federal Project Number(s): N/A
 
Federal Job Number(s): N/A
 
Location:  88th Avenue, 103rd Street to 87th Street in the Cities of Palos Hills and Hickory Hills
 
Board District:  17
 
Good(s) or Service(s):  Adjustment of Quantities and New Items
 
Fiscal Impact:  $173,169.46 decrease  
 
Accounts:  Motor Fuel Tax Fund Account 600-600
 
Summary: The Department of Transportation and Highways respectfully submits a change in plans and extra work on the above captioned project in the Cities of Palos Hills and Hickory Hills.
 
On 7/12/2011, your honorable Body awarded a contract to K-Five Construction Corporation, Lemont, Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.
 
The quantities as shown on the contract documents were estimated for bidding purposes only.  This change represents the difference between the estimated quantities and actual field quantities of work performed with savings due to less quantities being required for trench backfill, fire hydrant and water valve adjustments, metal post for signing, erosion control blanket, and inlet filters, per field conditions along with the assessment of erosion control deficiency deduction, and credit for various asphalt items.
 
New items were added for premium charges for overtime to accelerate project completion, modification of traffic signal controller at 95th Street, extension of pipe culvert on southeast radius at 96th Street, and placing landscape stone at various locations along sidewalk. end