PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): K-Five Construction Corporation, Lemont, Illinois
Action: Refer to the Committee of Roads and Bridges
Section: 03-W3017-03-FP
Contract Number(s): N/A
IDOT Contract Number(s): N/A
Federal Project Number(s): N/A
Federal Job Number(s): N/A
Location: 88th Avenue, 103rd Street to 87th Street in the Cities of Palos Hills and Hickory Hills
Board District: 17
Good(s) or Service(s): Adjustment of Quantities and New Items
Fiscal Impact: $173,169.46 decrease
Accounts: Motor Fuel Tax Fund Account 600-600
Summary: The Department of Transportation and Highways respectfully submits a change in plans and extra work on the above captioned project in the Cities of Palos Hills and Hickory Hills.
On 7/12/2011, your honorable Body awarded a contract to K-Five Construction Corporation, Lemont, Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.
The quantities as shown on the contract documents were estimated for bidding purposes only. This change represents the difference between the estimated quantities and actual field quantities of work performed with savings due to less quantities being required for trench backfill, fire hydrant and water valve adjustments, metal post for signing, erosion control blanket, and inlet filters, per field conditions along with the assessment of erosion control deficiency deduction, and credit for various asphalt items.
New items were added for premium charges for overtime to accelerate project completion, modification of traffic signal controller at 95th Street, extension of pipe culvert on southeast radius at 96th Street, and placing landscape stone at various locations along sidewalk. end