title
PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Project Type: Motor Fuel Tax Project
Request: Approval of Proposed Supplemental Improvement Resolution
Project: Central Avenue - Sauk Trail to US 30 (Lincoln Highway)
Location: Village of Matteson, Illinois
Section: 19-IICFR-03-ES
County Board District: 6
Centerline Mileage: 1.50 miles
Fiscal Impact: $2,000,000.00 (FY26 = $500,000.00; FY27 = $1,000,000.00; FY28 = $500,000.00)
Accounts: Motor Fuel Tax Fund: 11300.1500.29152.560019
Board Approved Date and Amount: 7/25/2019, $400,000.00; 9/22/2022, $1,300,000.00
Increased Amount: $2,000,000.00
Total Adjusted Amount: $3,700,000.00
Summary: The Department of Transportation and Highways respectfully requests approval of the proposed supplemental improvement resolution for work being done in the Village of Matteson. The supplemental resolution is appropriating funds for the full reconstruction of Central Avenue from Sauk Trail to Lincoln Highway (US Rte. 30) in the Village of Matteson in Cook County.
end