File #: 14-5303    Version: 1 Name: Dist 4 Sup Imp 03-7BLDG-05-MG
Type: Supplemental Improvement Resolution (Highway) Status: Approved
File created: 9/9/2014 In control: Roads and Bridges Committee (Inactive. There is now a Transportation Committee)
On agenda: 10/8/2014 Final action: 11/19/2014
Title: PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Project Type: Motor Fuel Tax Project Supplemental Improvement Request: Refer to the Committee of Roads and Bridges Project: New storage building and existing building rehabilitation for Maintenance District #4. Location: in the Village of Orland Park and Unincorporated Palos Township. Section: 03-7BLDG-05-MG County Board District: 17 Centerline Mileage: N/A Fiscal Impact: $1,700,000.00 Accounts: Motor Fuel Tax Fund 600-585 Account Board Approved Date and Amount: 11/4/2003, $6,000,000.00 Increased Amount: $1,700,000.00 Total Adjusted Amount: $7,700,000.00 Summary: This improvement, as proposed, consisted of construction of a new metal maintenance vehicle storage building as well as the rehabilitation of existing buildings and shall include excavation, foundations, fire suppression system instal...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
 
Department:  Transportation and Highways  
 
Project Type:   Motor Fuel Tax Project Supplemental Improvement   
 
Request:  Refer to the Committee of Roads and Bridges  
 
Project:  New storage building and existing building rehabilitation for Maintenance District #4.  
 
Location:  in the Village of Orland Park and Unincorporated Palos Township.  
 
Section:  03-7BLDG-05-MG
 
County Board District:  17  
 
Centerline Mileage:  N/A  
 
Fiscal Impact:  $1,700,000.00  
 
Accounts:  Motor Fuel Tax Fund 600-585 Account
 
Board Approved Date and Amount:  11/4/2003, $6,000,000.00  
 
Increased Amount:  $1,700,000.00  
 
Total Adjusted Amount:  $7,700,000.00
 
Summary:  
This improvement, as proposed, consisted of construction of a new metal maintenance vehicle storage building as well as the rehabilitation of existing buildings and shall include excavation, foundations, fire suppression system installation, mechanical, HVAC, plumbing and electrical appurtenances, storm drainage and sanitary system modifications, utility relocation, landscaping, existing roof and perimeter parapet wall replacement, design engineering by an outside engineer, in-house review, construction engineering and other necessary appurtenances to complete the project.
 
On 11/4/2003, your Honorable Body approved an Improvement Resolution appropriating $6,000,000.00.  Additional funding is needed due to subsequent expansion of the improvement scope to include additional building improvements and repairs, site plan changes and additional design engineering for LEED certification.  The construction was completed on 10/24/2007. This supplement improvement for the amount of $1,700,000.00 is necessary for accounting closure.  
end