title
PROPOSED CONTRACT AMENDMENT
Department(s): Department of Facilities Management
Vendor: Marco Supply Co. Inc. d/b/a Johnson Pipe & Supply Co., Chicago, Illinois
Request: Authorization for the Chief Procurement Officer to renew contract
Good(s) or Service(s): Saws and Saw Blades
Original Contract Period: 4/1/2021 - 3/31/2024, with one (1), two (2) year renewal option
Proposed Amendment Type: Renewal
Proposed Contract Period: 4/1/2024 - 3/31/2026
Total Current Contract Amount Authority: $282,849.55
Original Approval (Board or Procurement): Board, 3/18/2021, $282,849.55
Increase Requested: N/A
Previous Board Increase(s): N/A
Previous Chief Procurement Officer Increase(s): N/A
Previous Board Renewals: N/A
Previous Chief Procurement Officer Renewals: N/A X
Previous Board Extension(s): N/A
Previous Chief Procurement Officer Extension(s): N/A
Potential Fiscal Impact: N/A
Accounts: N/A
Contract Number(s): 2002-18306
Concurrences:
The contract-specific goal set on this contract was zero.
The Chief Procurement Officer concurs.
Summary: This final renewal will allow the Department of Facilities Management to continue to receive Saws and Saw Blades.
This contract was awarded through a publicly advertised competitive bidding process in accordance with the Cook County Procurement Code. Marco Supply Co. Inc. d/b/a Johnson Pipe & Supply Co. was the lowest, responsive, and responsible bidder.
end