PROPOSED PAYMENT APPROVAL
Department(s): Department of Capital Planning and Policy
Action: Request to Approve Payment
Payee: Paul Borg Construction Company, Chicago, Illinois
Good(s) or Service(s): Job Order Contracting (JOC) Services
Fiscal Impact: $305,747.72
Accounts: 11569.1031.11190.560105.00000.00000
11569.1031.11190.560107.00000.00000
Capital Improvement Program
Contract Number(s): 2185-11191 SPGC 11
Summary: The Department of Capital Planning and Policy respectfully requests approval of a one-time payment to Paul Borg Construction in the amount of $305,747.72. This final payment is related to completed work at the Bronzeville Health Center and was delayed due to negotiations of final closeout costs.