PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Plote Construction, Inc., Hoffman Estates, Illinois
Action: Completion of Construction Approval Resolution
Good(s) or Service(s): Construction Services.
Location of Project:
Group 1 - 2016
Pavement Preservation and Rehabilitation Program - North 2016
Lake Cook Road at Takeda Parkway
Mundhank Road-Barrington Road to Freeman Road,
East Frontage Road-Old Orchard Road to Glenview Road
West Frontage Road-Illinois Road to Orchard Lane
Section: 16-A8106-00-FP
County Board District: 13, 14 and 15
Contract Number: 1655-15887
Federal Project Number: N/A
Federal Job Number: N/A
Final Cost: $1,588,625.30
Percent Above or Below Construction Contract Bid Amount: -$610,985.35 or 27.8% below the Construction Engineering Contract Amount.
Summary: The Department of Transportation and Highways respectfully requests the approval of the Proposed Completion of Construction Approval Resolution. The decreases are attributed to the difference between the estimated quantities and actual field quantities of work performed with decrease in earth excavation, topsoil, sodding, pcc sidewalk items, hot-mix asphalt items and patching related items.
The proposed improvement consisted of grinding and overlaying of existing hot-mix asphalt pavement, patching, drainage improvements, curb and gutter replacement, grading and shaping ditches, sidewalk ADA improvements, traffic control and protection, shoulder repair, pavement markings and any collateral and auxiliary work as needed to complete the project has been completed.end