PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Triggi Construction, Inc., West Chicago, Illinois
Action: Completion of Construction Approval Resolution
Good(s) or Service(s): Construction and Construction Engineering
Location of Project: Group 2 - 2016
Pavement Preservation and Rehabilitation Program - South 2016
Kedzie Avenue Frontage Road-143rd Street to 141st Street
Kedzie Avenue at 163rd Street
Frontage Road at Crawford Avenue
Joe Orr Road-Cottage Grove Avenue to Stony Island Avenue
Sauk Trail at Richton Square Road
Sauk Trail at Lakewood Blvd./Blackhawk Drive
Flossmoor Road at Kedzie Avenue
Section: 16-B6735-00-PV
County Board District: 5 and 6
Contract Number: 1685-15879
Federal Project Number: N/A
Federal Job Number: N/A
Final Cost: $2,589,858.00, Motor Fuel Tax Account: 11300.1500.29150.560019
Percent Above or Below Construction Contract Bid Amount: $166,141.09 or 6.03% below the Construction Engineering Contract Amount.
Summary: The Department of Transportation and Highways respectfully request Approval of the Proposed Completion of Construction Approval Resolution for work done with Triggi Construction, Inc., West Chicago, Illinois. The proposed improvement consisted of grinding and overlaying of existing hot-mix asphalt pavement, diamond grinding of existing concrete pavement, patching, drainage improvements, curb and gutter replacement, grading and shaping ditches, sidewalk ADA improvements, traffic control and protection, pavement markings and any collateral and auxiliary work as needed to complete the project. The decreases are attributed to the difference between the estimated quantities and actual field quantities of work performed with decrease in hot-mix asphalt related items, patching related items, curb and gutter and joint repair special.