File #: 24-0647    Version: 1 Name: Improvement Resolution for 2023 Pavement Maintenance North (Plum Grove Road and Wagner Road)
Type: Improvement Resolution (Highway) Status: Approved
File created: 12/14/2023 In control: Transportation Committee
On agenda: 1/25/2024 Final action: 2/29/2024
Title: PROPOSED IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Project Type: Motor Fuel Tax Project Request: Approval of appropriation of Motor Fuel Tax Funds Project: 2023 Pavement Maintenance North Plum Grove Road and Wagner Road Location: Villages of Roselle, Elk Grove Village, Schaumburg, Hoffman Estates, Glenview, and Northfield Section: 23-PVMTN-00-PV County Board District(s): 14, 15, 17 Centerline Mileage: 5.17 miles Fiscal Impact: $19,000,000.00 Accounts: Motor Fuel Tax Fund: 11300.1500.29150.560019 Summary: The Department of Transportation and Highways respectfully requests approval of the proposed improvement resolution for work being done in Villages of Roselle, Elk Grove Village, Schaumburg, Hoffman Estates, Glenview, and Northfield. The project scope consists of curb and gutter removal and replacement, diamond grinding and patching, milling and resurfacing.
Indexes: JENNIFER (SIS) KILLEN, Superintendent, Department of Transportation and Highways

title

PROPOSED IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)

 

Department: Transportation and Highways

 

Project Type:  Motor Fuel Tax Project 

 

Request:  Approval of appropriation of Motor Fuel Tax Funds 

 

Project:  2023 Pavement Maintenance North Plum Grove Road and Wagner Road

 

Location:  Villages of Roselle, Elk Grove Village, Schaumburg, Hoffman Estates, Glenview, and Northfield

 

Section:  23-PVMTN-00-PV

 

County Board District(s):  14, 15, 17

 

Centerline Mileage:  5.17 miles

 

Fiscal Impact:  $19,000,000.00

 

Accounts:  Motor Fuel Tax Fund: 11300.1500.29150.560019

 

Summary:  The Department of Transportation and Highways respectfully requests approval of the proposed improvement resolution for work being done in Villages of Roselle, Elk Grove Village, Schaumburg, Hoffman Estates, Glenview, and Northfield. The project scope consists of curb and gutter removal and replacement, diamond grinding and patching, milling and resurfacing. 