title
PROPOSED CONTRACT AMENDMENT
Department(s): Office of Capital Planning and Policy
Vendor: Faithful + Gould, Chicago, Illinois
Request: Authorization for the Chief Procurement Officer to extend and increase contract
Good(s) or Service(s): Construction Management Services
Original Contract Period: 5/8/2013 - 12/31/2014
Proposed Contract Period Extension: 1/1/2015 - 7/31/2015
Total Current Contract Amount Authority: $963,999.00
Original Approval (Board or Procurement): 5/8/2013, $963,999.00
Previous Board Increase(s) or Extension(s): N/A
Previous Chief Procurement Officer Increase(s) or Extension(s): N/A
This Increase Requested: $385,824.00
Potential Fiscal Impact: FY 2015 $ 385,824.00
Accounts: 20000 - County Physical Plant
Contract Number(s): 13-88-066
Concurrences:
Vendor has met the Minority and Women Business Enterprise Ordinance.
The Chief Procurement Officer concurs.
Summary: The Construction Management Service required in order to complete this project will necessitate multiple work shifts, as the General Contractor is utilizing their manpower on 3 shifts / day in order to meet their completion date of 7/6/2015. We are requesting an additional fee to cover the services to be in alignment with the construction activities.
end