File #: 15-1705    Version: 1 Name: 15-1705 Sup Imp 167th 06-B5928-02- RP
Type: Improvement Resolution (Highway) Status: Approved
File created: 2/10/2015 In control: Roads and Bridges Committee (Inactive. There is now a Transportation Committee)
On agenda: 4/1/2015 Final action: 4/29/2015
Title: PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Project Type: Motor Fuel Tax Project Supplemental Improvement Resolution Request: Approval of a supplemental improvement resolution appropriating additional funds upon the recommendation of the Committee on Roads and Bridges Project: Additional funding is needed due to expansion of the scope to complete the modernization of traffic signals. The project was completed on 9/7/2007, and this supplement is necessary for accounting closure. Location: 167th Street, Kilbourn Avenue to Park Avenue in the Village of Hazel Crest and Cities of Country Club Hills and Markham Section: 06-B5928-02-RP County Board District: 5 Centerline Mileage: N/A Fiscal Impact: $111,000.00 Accounts: Motor Fuel Tax Fund (600 - 585 Account) Board Approved Date and Amount: 2/15/2006, $2,400,000.00 Increased Amount: $111,000.00 Total ...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
 
Department:  Transportation and Highways  
 
Project Type:  Motor Fuel Tax Project Supplemental Improvement Resolution   
 
Request:  Approval of a supplemental improvement resolution appropriating additional funds upon the recommendation of the Committee on Roads and Bridges  
 
Project:  Additional funding is needed due to expansion of the scope to complete the modernization of traffic signals.  The project was completed on 9/7/2007, and this supplement is necessary for accounting closure.  
 
Location:  167th Street, Kilbourn Avenue to Park Avenue in the Village of Hazel Crest and Cities of Country Club Hills and Markham
 
Section:  06-B5928-02-RP  
 
County Board District:  5  
 
Centerline Mileage:   N/A  
 
Fiscal Impact:  $111,000.00  
 
Accounts:  Motor Fuel Tax Fund (600 - 585 Account)  
 
Board Approved Date and Amount:  2/15/2006, $2,400,000.00
 
Increased Amount:  $111,000.00
 
Total Adjusted Amount:  $2,511,000.00  
 
Summary:  This improvement, as proposed, consisted of the full depth concrete  patching of the existing pavement, curb and gutter repair, adjustments or reconstruction of existing drainage structures; also, formed concrete repairs on parapet walls of the bridge over I-57, replacement of existing Strip Seal Joint Assemblies and patching of the wearing surface; remediation/replacement of isolated areas of settled pavement along 80th Avenue between 183rd Street and 171st Street; pavement marking, landscaping, engineering and other necessary highway appurtenances.
 