title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Geske & Sons, Inc., Crystal Lake, Illinois
Action: Approval
Good(s) or Service(s): Palatine Township 2012 Various. The work, consisting of milling and resurfacing existing Hot Mix Asphalt pavement patching, pavement markings and traffic protection.
Location of Project: Palatine Township 2012 Various Locations
Section: 12-25156-90-RS
County Board District: #14
Contract Number: 12-28-221
Federal Project Number: N/A
Federal Job Number: N/A
Final Cost: $370,917.85 from the Motor Fuel Tax Fund: 600-600 Account
Percent Above or Below Construction Contract Bid Amount: -$3,535.95 or 0.94% below the Construction Contract Bid
Summary:
On July 10, 2012, your Honorable Body awarded a contract to Geske & Sons, Inc., Crystal Lake, Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.
The awarded contract amount of this project was $374,503.80 and the final construction cost is $370,917.85. This change represents the difference between the estimated quantities and actual field quantities of work performed.
end