File #: 14-6042    Version: 1 Name: Supl Imp Res 103rd 87-B4522-03-RP
Type: Supplemental Improvement Resolution (Highway) Status: Approved
File created: 10/17/2014 In control: Board of Commissioners
On agenda: 11/19/2014 Final action: 11/19/2014
Title: PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Project Type: Motor Fuel Tax Project Supplemental Improvement Resolution Request: Refer to the Committee of Roads and Bridges Project: Pavement Widening and Reconstruction Location: 103rd Street, Kean Avenue to Roberts Road in the City of Palos Hills Section: 87-B4522-03-RP Federal Project No: STPM-7003(591) State Job No: C-91-111-98 and C-89-001-98 County Board District: 17 Centerline Mileage: N.A. Fiscal Impact: $781,000.00) Accounts: Motor Fuel Tax Fund (600-585 Account) Board Approved Date and Amount: 11/16/1987 $4,700,000.00 Increased Amount: $781,000.00 Total Adjusted Amount: $5,481,000.00 Summary: This improvement, as proposed, shall be for the widening and/or reconstruction of the existing two-lane pavement to an adequate two-lane and four-lane pavement including grading, paving, dr...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
 
Department:  Transportation and Highways  
 
Project Type:  Motor Fuel Tax Project Supplemental Improvement Resolution  
 
Request:  Refer to the Committee of Roads and Bridges  
 
Project:  Pavement Widening and Reconstruction  
 
Location:  103rd Street, Kean Avenue to Roberts Road in the City of Palos Hills  
 
Section:  87-B4522-03-RP Federal
 
Project No: STPM-7003(591)
 
State Job No: C-91-111-98 and C-89-001-98
 
County Board District:  17
 
Centerline Mileage:  N.A.
 
Fiscal Impact:  $781,000.00)  
 
Accounts:  Motor Fuel Tax Fund (600-585 Account)  
 
Board Approved Date and Amount:  11/16/1987 $4,700,000.00
 
Increased Amount:  $781,000.00  
 
Total Adjusted Amount:  $5,481,000.00  
 
Summary:  This improvement, as proposed, shall be for the widening and/or reconstruction of the existing two-lane pavement to an adequate two-lane and four-lane pavement including grading, paving, drainage facilities, curb and gutter, median, channelization, traffic signals, culvert widening, right-of-way, partial engineering and other necessary highway appurtenances.
 
On 11/16/1987, your Honorable Body approved an Improvement Resolution in the amount of $4,700,000.00.  Additional funding is needed due to expansion of the improvement scope to include construction of a triple box culvert, concrete sidewalks, street lighting installation, driveway construction, landscaping and additional engineering due to the expanded scope and significantly higher costs due to the lapse in time from the 1987 Improvement Resolution approval to the 1999 contract letting date.  The construction was completed on 6/112001, and this supplement is necessary for accounting closure.  