File #: 15-3277    Version: 1 Name: A. Lamp Concrete Contractors, Barrington Illinois
Type: Completion of Construction Approval Resolution (Highway) Status: Approved
File created: 5/7/2015 In control: Board of Commissioners
On agenda: 6/10/2015 Final action: 6/10/2015
Title: PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): A. Lamp Concrete Contractors, Barrington Illinois Action: Approval Good(s) or Service(s): Concrete patching, diamond grinding, concrete curb and gutter, medians, sidewalk, storm sewer improvement, pavement marking, signing, landscaping, traffic protection, detector loop and all other work as required to complete the improvement. Location of Project: Schaumburg Road, Barrington Road to Roselle Road in the Villages of Hoffman Estates and Schaumburg Section: 11-A6607-04-RP County Board District: 15 Contract Number: N/A Federal Project Number: N/A Federal Job Number: N/A Final Cost: $3,497,321.60 Percent Above or Below Construction Contract Bid Amount: 17.3% above the Construction Bid Amount. Summary: On 2/5/2013 your Honorable Body awarded a contract to A. Lamp Concrete Contractors, Inc...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION
(TRANSPORTATION AND HIGHWAYS)
 
Department: Transportation and Highways
 
Other Part(ies):  A. Lamp Concrete Contractors, Barrington Illinois  
 
Action:  Approval
 
Good(s) or Service(s):  Concrete patching, diamond grinding, concrete curb and gutter, medians, sidewalk, storm sewer improvement, pavement marking, signing, landscaping, traffic protection, detector loop and all other work as required to complete the improvement.
 
Location of Project:  Schaumburg Road, Barrington Road to Roselle Road in the Villages of Hoffman Estates and Schaumburg
 
Section:  11-A6607-04-RP  
 
County Board District:  15  
 
Contract Number:  N/A
 
Federal Project Number:  N/A
 
Federal Job Number:  N/A
 
Final Cost:  $3,497,321.60
 
Percent Above or Below Construction Contract Bid Amount:  17.3% above the Construction Bid Amount.
 
Summary:  On 2/5/2013 your Honorable Body awarded a contract to A. Lamp Concrete Contractors, Inc., Barrington, Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.
 
The work, consisting of concrete patching, diamond grinding, concrete curb and gutter, medians, sidewalk, storm sewer improvement, pavement marking, signing, landscaping, traffic protection, detector loop and all other work as required to complete the improvement, has been completed under the supervision and to the satisfaction of the Superintendent.
 
The additions are attributed to the difference between the estimated quantities and actual field quantities of work performed with increases in concrete patching, sodding and topsoil which were required to complete the project due to existing field conditions
 
 
 
end