File #: 14-0008    Version: 1 Name: 1-15-2014 12-4-2013 C & P 170th 08-B5935-05-RP
Type: Change in Plans and Extra Work (Highway) Status: Approved
File created: 11/7/2013 In control: Administration, Bureau of
On agenda: 1/15/2014 Final action: 1/15/2014
Title: PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): Capitol Cement Company, Inc., Chicago Illinois Action: Request approval Section: 08-B5935-05-RP Location: 170th (167th) Street, Bishop Ford Freeway to Burnham Avenue in the Villages of South Holland and Lansing Board District: 6 Good(s) or Service(s): Final Adjustment of Quantities and New Item Fiscal Impact: $53,378.24 (decrease) Accounts: 600-600 (Motor Fuel Tax) Additional Details: The quantities as shown on the contract documents were estimated for bidding purposes only. This change represents the difference between the estimated quantities and actual field quantities of work performed. Since added work is paid under the particular items of work performed, contract extra work item is eliminated. A new item is required for repair of existing catch basins and pipes, per field conditions.
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)
 
Department: Transportation and Highways
 
Other Part(ies):  Capitol Cement Company, Inc., Chicago Illinois
 
Action:  Request approval
 
Section:  08-B5935-05-RP
 
Location:  170th (167th) Street, Bishop Ford Freeway to Burnham Avenue in the Villages of South Holland and Lansing
 
Board District:  6
 
Good(s) or Service(s):  Final Adjustment of Quantities and New Item  
 
Fiscal Impact:  $53,378.24 (decrease)  
 
Accounts:  600-600 (Motor Fuel Tax)
 
Additional Details:  The quantities as shown on the contract documents were estimated for bidding purposes only.  This change represents the difference between the estimated quantities and actual field quantities of work performed. Since added work is paid under the particular items of work performed, contract extra work item is eliminated. A new item is required for repair of existing catch basins and pipes, per field conditions.
end