File #: 13-1607    Version: 1 Name: Triggi Construction, Inc.
Type: Completion of Construction Approval Resolution (Highway) Status: Approved
File created: 9/6/2013 In control: Administration, Bureau of
On agenda: 10/2/2013 Final action: 10/2/2013
Title: PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Department of Transportation and Highways Other Part(ies): Triggi Construction, Inc., West Chicago, Illinois Action: Approval Good(s) or Service(s): Construction Location of Project: Bartlett Road, Lake Street to Golf Road , in the Village of Hoffman Estates Section: 11-V4738-02-RP County Board District: 15 Contract Number: 11-28-186I Federal Project Number: N/A Federal Job Number: N/A Final Cost: $3,150,910.21 Percent Above or Below Construction Contract Bid Amount: 5%, $150,825.61 (addition) Summary Respectfully submit to your Honorable Body and recommend for adoption a resolution approving the construction of the above captioned project in the Village of Hoffman Estates. On March 1, 2012, your Honorable Body awarded a contract for the aforesaid improvement to be completed in accordance with the plans and specifications. ...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
 
Department:  Department of Transportation and Highways
 
Other Part(ies):  Triggi Construction, Inc., West Chicago, Illinois
 
Action:  Approval
 
Good(s) or Service(s):  Construction  
 
Location of Project:  Bartlett Road, Lake Street to Golf Road , in the Village of Hoffman Estates
 
Section:   11-V4738-02-RP
 
County Board District:  15
 
Contract Number:  11-28-186I
 
Federal Project Number:  N/A
 
Federal Job Number:  N/A
 
Final Cost:  $3,150,910.21
 
Percent Above or Below Construction Contract Bid Amount:  5%, $150,825.61 (addition)
 
Summary  Respectfully submit to your Honorable Body and recommend for adoption a resolution approving the construction of the above captioned project in the Village of Hoffman Estates.  
 
On March 1, 2012, your Honorable Body awarded a contract for the aforesaid improvement to be completed in accordance with the plans and specifications.
 
The work, consisting of repairing the existing concrete pavement with patching along with diamond grinding, repairing and replacing the damaged combination concrete curb and gutter, median repair, crack and joint sealing, drainage repairs and adjustments, removal and replacement of raised reflective pavement markers, replacement of loop detectors, pavement marking, traffic protection and miscellaneous appurtenances, has been completed under the supervision and to the satisfaction of the Superintendent of Highways.
 
The awarded contract amount of this project was $3,000,084.60 and final construction cost is $3,150,910.21. The increase was due to additional quantities of patching, drainage related items and driveway pavement removal and replacement, which were required per field conditions.
end