File #: 14-3133    Version: 1 Name: 6-18-2014 Sup Imp Devon 01-B1113-06-RP
Type: Supplemental Improvement Resolution (Highway) Status: Approved
File created: 5/12/2014 In control: Roads and Bridges Committee (Inactive. There is now a Transportation Committee)
On agenda: 6/18/2014 Final action: 7/23/2014
Title: PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Project Type: Motor Fuel Tax Project Second Supplemental Improvement Resolution Request: Refer to the Committee of Roads and Bridges Project: Resurfacing existing concrete pavement, bridge repair etc. and engineering costs for account closure. Location: Devon Avenue, Rohlwing Road to Park Boulevard in the Villages of Elk Grove and Itasca Section: 01-B1113-06-RP County Board District: 15 Centerline Mileage: 0.70 miles Fiscal Impact: $925,000.00 Accounts: Motor Fuel Tax Fund (600-585 Account) Board Approved Date and Amount: $1,378,000.00 (Original amount 5/1/2001:$750,000.00; Previous Increase 9/5/2002: $628,000.00) Increased Amount: $925,000.00 Total Adjusted Amount: $2,303,000.00 Summary: .On 5/1/2001 the Cook County Board of Commissioners approved the original Improvement Resolution which appropriate...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways
title
PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
 
Department:  Transportation and Highways  
 
Project Type:  Motor Fuel Tax Project Second Supplemental Improvement Resolution  
 
Request:  Refer to the Committee of Roads and Bridges
 
Project:  Resurfacing existing concrete pavement, bridge repair etc. and engineering costs for account closure.  
 
Location:  Devon Avenue, Rohlwing Road to Park Boulevard in the Villages of Elk Grove and Itasca
 
Section:  01-B1113-06-RP
 
County Board District:  15
 
Centerline Mileage:  0.70 miles
 
Fiscal Impact:  $925,000.00
 
Accounts:  Motor Fuel Tax Fund (600-585 Account)  
 
Board Approved Date and Amount:  $1,378,000.00 (Original amount 5/1/2001:$750,000.00; Previous Increase 9/5/2002: $628,000.00)
 
Increased Amount:  $925,000.00  
 
Total Adjusted Amount:  $2,303,000.00
 
Summary:  .On 5/1/2001 the Cook County Board of Commissioners approved the original Improvement Resolution which appropriated $750,000.00 towards completion of the project and on 9/5/2002 and additional $682,000.00 was approved.
 
This Second supplement is required for engineering and additional work not anticipated in the original contract and necessary for accounting closure.  