title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Gallagher Asphalt Corporation, Thornton, Illinois
Action: Approval
Good(s) or Service(s): Milling of the asphalt surface on 108th Avenue from 179th Street to 167th Place, cold in-place recycling of the pozzolanic base, base repair with patches, resurfacing with binder and surface course, drainage additions and adjustments, topsoil and sodding, pavement marking, detour routing, traffic protection and other related road work required to complete the improvement.
Location of Project: 108th Avenue, 179th Street to 163rd Place in the Village of Orland Park
Section: Section: 11-W7507-04-FP
County Board District: 17
Contract Number: 12-28-059
Federal Project Number: N/A
Federal Job Number: N/A
Final Cost: $2,149,736.42
Percent Above or Below Construction Contract Bid Amount: 9.08% below the construction contract bid.
Summary: On 5/1/2012 the contract was awarded for the amount $2,364,393.33 and the final construction cost is $2,149,736.42. The savings is attributed to the project specific cold in-place recycling process which determined that the materials reclaimed from the existing pavement required the addition of less bituminous material and also provided roadway rehabilitation at a cross-slope that reduced the amount of pavement replacement, binder and leveling binder required.
end