File #: 15-5979    Version: 1 Name: Motor Fuel Tax Project Improvement Resolution Lake Cook Road, Weiland Road to Hastings Lane, Aptakisic Road from Buffalo Grove Road to McHenry Road/IL 83, Weiland Road from Buffalo Grove Road to Woodstone Drive, Buffalo Grove Road at Weiland Road, McHenry
Type: Improvement Resolution (Highway) Status: Approved
File created: 10/8/2015 In control: Board of Commissioners
On agenda: 10/28/2015 Final action: 10/28/2015
Title: PROPOSED IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Project Type: Motor Fuel Tax Project Improvement Resolution Request: Approval of appropriation of Motor Fuel Tax Funds Project: This improvement, as proposed, will consist of reconstruction of the existing pavement with Portland Cement Concrete pavement and shall include right-of-way acquisition, pavement removal, concrete curb and gutter removal and replacement, storm sewer installation, detention pond construction, tree removal, bridge removal and replacement, Buffalo Creek realignment, street lighting, traffic signal installation, signing, traffic protection, pavement marking, landscaping, engineering and other necessary highway appurtenances. A portion of the costs of the Lake Cook Road improvement will be reimbursable from Federal funds. Location: Lake Cook Road, Weiland Road to Hastings Lane, Aptakisic Road from Buffalo Grove Road to McHenry Road/IL 83,...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways

title

PROPOSED IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)

 

Department: Transportation and Highways

 

Project Type:   Motor Fuel Tax Project Improvement Resolution  

 

Request:  Approval of appropriation of Motor Fuel Tax Funds 

 

Project:   This improvement, as proposed, will consist of reconstruction of the existing pavement with Portland Cement Concrete pavement and shall include right-of-way acquisition, pavement removal, concrete curb and gutter removal and replacement, storm sewer installation, detention pond construction, tree removal, bridge removal and replacement, Buffalo Creek realignment, street lighting, traffic signal installation, signing, traffic protection, pavement marking, landscaping, engineering and other necessary highway appurtenances.  A portion of the costs of the Lake Cook Road improvement will be reimbursable from Federal funds.

 

Location:  Lake Cook Road, Weiland Road to Hastings Lane, Aptakisic Road from Buffalo Grove Road to McHenry Road/IL 83, Weiland Road from Buffalo Grove Road to Woodstone Drive, Buffalo Grove Road at Weiland Road, McHenry Road/IL 83 at Weiland Road in the Village of Buffalo Grove and the Village of Wheeling

 

Section:  14-A5015-03RP

 

County Board District(s):  14

 

Centerline Mileage:  2.23

 

Fiscal Impact:  $45,200,000.00

 

Accounts:  Motor Fuel Tax Fund: (600-585 Account)

 

Summary:  This improvement will promote economic development and regional mobility, and is needed to protect the public investment in the highway system and provide a safe, efficient and sustainable highway.