File #: 16-2491    Version: 1 Name: The Gordian Group Inc, Mauldin, South Carolina
Type: Contract Amendment Status: Approved
File created: 3/29/2016 In control: Asset Management Committee
On agenda: 4/13/2016 Final action: 5/11/2016
Title: PROPOSED CONTRACT AMENDMENT Department(s): Capital Planning and Policy, Facilities Management, Transportation and Highways Vendor: The Gordian Group, Inc., Greenville, South Carolina Request: Authorization for the Chief Procurement Officer to renew and increase contract Good(s) or Service(s): Professional Services Original Contract Period: 5/1/2012 - 4/30/2015 with two (2), one (1) year renewal options Proposed Contract Period Extension: 5/1/2016 - 4/30/2017 Total Current Contract Amount Authority: $3,550,000.00 Original Approval (Board or Procurement): 5/14/2012, $1,050,000.00 Previous Board Increase(s) or Extension(s): 9/10/2014, $2,500,000.00 Previous Chief Procurement Officer Increase(s) or Extension(s): 4/24/2015, 5/1/2015 - 4/30/2016 This Increase Requested: $3,500,000.00 Potential Fiscal Impact: FY 2016 $1,750,000.00, FY 2017 $1,750,000.00 Accounts: Capital Improvement Program - 580 Contract Number(s): 11-2...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways, (Inactive) PHIL BOOTHBY, Director, Office of Capital Planning and Policy , BILQIS JACOBS-EL, Director, Department of Facilities Management
title
PROPOSED CONTRACT AMENDMENT

Department(s): Capital Planning and Policy, Facilities Management, Transportation and Highways

Vendor: The Gordian Group, Inc., Greenville, South Carolina

Request: Authorization for the Chief Procurement Officer to renew and increase contract

Good(s) or Service(s): Professional Services

Original Contract Period: 5/1/2012 - 4/30/2015 with two (2), one (1) year renewal options

Proposed Contract Period Extension: 5/1/2016 - 4/30/2017

Total Current Contract Amount Authority: $3,550,000.00

Original Approval (Board or Procurement): 5/14/2012, $1,050,000.00

Previous Board Increase(s) or Extension(s): 9/10/2014, $2,500,000.00

Previous Chief Procurement Officer Increase(s) or Extension(s): 4/24/2015, 5/1/2015 - 4/30/2016

This Increase Requested: $3,500,000.00

Potential Fiscal Impact: FY 2016 $1,750,000.00, FY 2017 $1,750,000.00

Accounts: Capital Improvement Program - 580

Contract Number(s): 11-28-043

Concurrences:
The vendor has met the Minority and Women Owned Business Enterprise Ordinance.

The Chief Procurement Officer concurs.

Summary: The objective of the JOC program is to provide an alternate procurement method to enable the County to rapidly engage construction project simultaneously.

The request to increase in the amount of $3,500,000.00 is based on the available capacity of the JOC Contractors. The Gordian Group's fee for the services provided is assessed as a percentage of the value of construction procured by the County through the JOC program. The increase requested through this amendment was calculated by the applying The Gordian Group's percent fee against the total value of construction that is available to be purchased by the County through its JOC contracts. The County is under no obligation to expend the amount requested, and is only obligated to pay The Gordian Group's fee when the construction work is procured through the JOC progr...

Click here for full text