title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): F.H. Paschen S.N. Nielsen Associates, Chicago, Illinois
Action: Approval of the Proposed Completion of Construction Approval Resolution
Good(s) or Service(s): Completion of Construction -Pavement Improvements
Location of Project: Bell Road -131 Street to 115th Street, Busse Road - Central Road to Golf Road, Penny Road - New Sutton Road (IL 59) to Algonquin Road (IL 62) and 79th Street at County Line Road, in the Village of Phoenix and the City of Harvey.
Section: 13-W1813-06-RS
County Board District: 14, 15 and 17
Contract Number: 12-23-340 HS7
Federal Project Number: N/A
Federal Job Number: N/A
Final Cost: $2,046,828.21
Percent Above or Below Construction Contract Bid Amount: 0.00%
Summary: The Department of Transportation and Highways respectfully requests approval of the Proposed Completion of Construction Approval Resolution for Pavement Improvement in the Village of Phoenix and the City of Harvey.
On 10/3/2013 the Chief Procurement Officer awarded a contract to F.H. Paschen S.N. Nielsen Associates, Chicago, Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.
The JOC-improvement consisted of remedial/patching of isolated areas of deteriorated pavement and included milling and resurfacing the existing pavement using hot-mix asphalt materials, pavement patching as needed, traffic control and protection, pavement markings, removal and replacement of traffic signal detector loops, landscaping, engineering and other necessary highway appurtenances.
The awarded contract amount of this project was $2,046,828.21 and the final construction cost is $2,046,828.21.
end