File #: 19-1676    Version: 1 Name: Plote Construction, Inc., Hoffman Estates, Illinois Completion of Construction Resolution Plote Cosntruction, Inc. 1655-15887
Type: Completion of Construction Approval Resolution (Highway) Status: Approved
File created: 2/6/2019 In control: Board of Commissioners
On agenda: 4/25/2019 Final action: 4/25/2019
Title: PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): Plote Construction, Inc., Hoffman Estates, Illinois Action: Completion of Construction Approval Resolution Good(s) or Service(s): Construction Services. Location of Project: Group 1 - 2016 Pavement Preservation and Rehabilitation Program - North 2016 Lake Cook Road at Takeda Parkway Mundhank Road-Barrington Road to Freeman Road, East Frontage Road-Old Orchard Road to Glenview Road West Frontage Road-Illinois Road to Orchard Lane Section: 16-A8106-00-FP County Board District: 13, 14 and 15 Contract Number: 1655-15887 Federal Project Number: N/A Federal Job Number: N/A Final Cost: $1,588,625.30 Percent Above or Below Construction Contract Bid Amount: -$610,985.35 or 27.8% below the Construction Engineering Contract Amount. Summary: The Department of Transportation and Highways respectfully requests the approval of th...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways

title

PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)

 

Department: Transportation and Highways

 

Other Part(ies):  Plote Construction, Inc., Hoffman Estates, Illinois 

 

Action:  Completion of Construction Approval Resolution

 

Good(s) or Service(s):  Construction Services.

 

Location of Project: 

Group 1 - 2016

Pavement Preservation and Rehabilitation Program - North 2016

Lake Cook Road at Takeda Parkway

Mundhank Road-Barrington Road to Freeman Road,

East Frontage Road-Old Orchard Road to Glenview Road

West Frontage Road-Illinois Road to Orchard Lane

 

Section:  16-A8106-00-FP

 

County Board District:  13, 14 and 15 

 

Contract Number:  1655-15887

 

Federal Project Number:  N/A

 

Federal Job Number:  N/A

 

Final Cost:  $1,588,625.30

 

Percent Above or Below Construction Contract Bid Amount:  -$610,985.35 or 27.8% below the Construction Engineering Contract Amount.

 

Summary: The Department of Transportation and Highways respectfully requests the approval of the Proposed Completion of Construction Approval Resolution. The decreases are attributed to the difference between the estimated quantities and actual field quantities of work performed with decrease in earth excavation, topsoil, sodding, pcc sidewalk items, hot-mix asphalt items and patching related items.

 

The proposed improvement consisted of grinding and overlaying of existing hot-mix asphalt pavement, patching, drainage improvements, curb and gutter replacement, grading and shaping ditches, sidewalk ADA improvements, traffic control and protection, shoulder repair, pavement markings and any collateral and auxiliary work as needed to complete the project has been completed.end