File #: 20-3821    Version: 1 Name: Gallagher Asphalt Corporation, Thornton, Illinois
Type: Completion of Construction Approval Resolution (Highway) Status: Approved
File created: 8/19/2020 In control: Board of Commissioners
On agenda: 10/22/2020 Final action: 10/22/2020
Title: PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): Gallagher Asphalt Corporation, Thornton, Illinois Action: Completion of Construction Approval Resolution Good(s) or Service(s): Construction Services Location of Project: Pavement Reservation and Rehabilitation Program - South 2019; Sauk Trail from Governors Highway to West of Lakewood Boulevard; Kedzie Avenue from County Air Drive to 147th Street; Stony Island Avenue from Joe Orr Road to Glenwood Lansing Road; Harlem Avenue from Steger Road to Laraway Road / Sauk Trail Section: 19-PPRPS-00-PV County Board District: 5 & 6 Contract Number: 1955-17738 Federal Project Number: N/A Federal Job Number: N/A Final Cost: $3,429,788.78 Fund: Motor Fuel Tax: 11300.1500.29150.560019 Percent Above or Below Construction Contract Bid Amount: $777,959.70 or 29.3% above Construction Contract Bid Amount Summary: The Department ...
Indexes: (Inactive) JOHN YONAN, P.E., Superintendent, Department of Transportation and Highways

title

PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)

 

Department: Transportation and Highways

 

Other Part(ies):  Gallagher Asphalt Corporation, Thornton, Illinois

 

Action:  Completion of Construction Approval Resolution

 

Good(s) or Service(s):  Construction Services 

 

Location of Project:                       Pavement Reservation and Rehabilitation Program - South 2019; Sauk Trail from Governors Highway to West of Lakewood Boulevard; Kedzie Avenue from County Air Drive to 147th Street; Stony Island Avenue from Joe Orr Road to Glenwood Lansing Road; Harlem Avenue from Steger Road to Laraway Road / Sauk Trail

 

Section:  19-PPRPS-00-PV

 

County Board District:  5 & 6

 

Contract Number:  1955-17738

 

Federal Project Number:  N/A  

 

Federal Job Number:  N/A

 

Final Cost:  $3,429,788.78

 

Fund:  Motor Fuel Tax: 11300.1500.29150.560019 

 

Percent Above or Below Construction Contract Bid Amount:  $777,959.70 or 29.3% above Construction Contract Bid Amount

 

Summary:  The Department of Transportation and Highways respectfully submits the Proposed Completion of Construction for work done by Gallagher Asphalt Corporation, Thornton, Illinois. The proposed improvement consisted of grinding and overlaying of the existing hot-mix asphalt pavement, patching, diamond grinding of existing concrete pavement, sidewalk ADA improvements, drainage repairs and adjustments, curb and gutter replacement,   guardrail removal and replacement, traffic control and protection, pavement markings and any collateral and auxiliary work as needed to complete the project has been completed under the supervision and satisfaction of the Superintendent.

 

The increases are attributed to the difference between the estimated quantities and actual field quantities of work performed with additional quantities required for asphalt items, combination curb and gutter items, pavement patching items, modified urethane pavement marking, and storm sewer items.

end