File #: 21-1538    Version: 1 Name: Change in Plans for 1999-17919 West Lake / Dempster
Type: Change in Plans and Extra Work (Highway) Status: Approved
File created: 2/9/2021 In control: Transportation Committee
On agenda: 3/18/2021 Final action: 6/24/2021
Title: PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS) Department: Transportation and Highways Other Part(ies): A Lamp Concrete Contractors, Inc., Schaumburg, Illinois Action: Refer to Transportation Committee Section: 19-A5918-00-PV Contract Number(s): 1999-17919 IDOT Contract Number(s): N/A Federal Project Number(s): N/A Federal Job Number(s): N/A Location: West Lake Avenue - Wolf Road to Landwehr Road Dempster Street - Elmhurst Road to Wolf Road Board District: 9, 14 & 17 Good(s) or Service(s): Construction Services Fiscal Impact: $309,476.01 increase Accounts: Motor Fuel Tax: 11300.1500.29150.560019 Summary: The Department of Transportation and Highways respectfully requests approval of the proposed Change in Plans and Extra work on West Lake Avenue to be referred to Committee. The proposed improvement consisted of grinding and overlying of existing hot-mix asphalt pavement, patching, drainage improvements, curb and gutter replacement, ...
Indexes: JENNIFER (SIS) KILLEN, Superintendent, Department of Transportation and Highways

title

PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)

 

Department: Transportation and Highways

 

Other Part(ies):  A Lamp Concrete Contractors, Inc., Schaumburg, Illinois  

 

Action:  Refer to Transportation Committee

 

Section:  19-A5918-00-PV

 

Contract Number(s): 1999-17919

 

IDOT Contract Number(s): N/A

 

Federal Project Number(s): N/A

 

Federal Job Number(s): N/A

 

Location: 

West Lake Avenue - Wolf Road to Landwehr Road

Dempster Street - Elmhurst Road to Wolf Road

 

Board District:  9, 14 & 17

 

Good(s) or Service(s):  Construction Services 

 

Fiscal Impact:  $309,476.01 increase 

 

Accounts:  Motor Fuel Tax: 11300.1500.29150.560019

 

Summary: The Department of Transportation and Highways respectfully requests approval of the proposed Change in Plans and Extra work on West Lake Avenue to be referred to Committee. The proposed improvement consisted of grinding and overlying of existing hot-mix asphalt pavement, patching, drainage improvements, curb and gutter replacement, traffic control and protection, pavement markings and collateral and auxiliary work as needed to complete the project.

 

The quantities as shown on the contract documents were estimated for bidding purposes only. This change represents the difference between the estimated quantities and actual field quantities of work performed with additional quantities required for welded wire reinforcement, combination curb and gutter items, PCC sidewalk items, pavement patching items, storm sewers items, and underground conduits.

 

New items were added for traffic signal posts, frames and grates, push button extension, sign panel type 2, base preparation/cleaning cracks and joints for mixture material, Pedestrian Refuge Island, HMA/brick driveway replacement, bituminous material tack coat, filling removed raised reflective markers with epoxy, and structure repair.end