File #: 21-4957    Version: 1 Name: Amendment to a Previously Approved Item for DoTH
Type: Amendment to a Previously Approved Item Status: Approved
File created: 9/1/2021 In control: Board of Commissioners
On agenda: 9/23/2021 Final action: 9/23/2021
Title: PROPOSED PREVIOUSLY APPROVED ITEM AMENDMENT Department: Transportation and Highways Request: Amend Original Value and Scope of Work Item Number: 21-3892 Fiscal Impact: $1,302,599.00 Account(s): Motor Fuel Tax: 11856.1500.29150.540136 Original Text of Item: Contract Value of $1,431,099.00 to be spent in FY2021 for $471,099.00, FY2022 for $464,500.00, and FY2021 for $495,500.00. The Department of Transportation and Highways respectfully requests approval to amend a previously approved item. This previously approved items is a contract between the Department and Azteca Systems Inc., Sandy, Utah for Cityworks Software License and Maintenance. The cost has been reduced to $1,302,599.00 with annual fiscal impacts to FY2021 of $417,599.00, FY2022 of $427,000.00, and FY2023 of $458,000.00. While the scope of work remains unchanged, the current hosting environment, an on-premises server, will continue to be used up until the time that the transition to the cloud can be...
Indexes: JENNIFER (SIS) KILLEN, Superintendent, Department of Transportation and Highways

title

PROPOSED PREVIOUSLY APPROVED ITEM AMENDMENT

 

Department:  Transportation and Highways 

 

Request:  Amend Original Value and Scope of Work 

 

Item Number:  21-3892 

 

Fiscal Impact:  $1,302,599.00 

 

Account(s):  Motor Fuel Tax: 11856.1500.29150.540136 

 

Original Text of Item:  Contract Value of $1,431,099.00 to be spent in FY2021 for $471,099.00, FY2022 for $464,500.00, and FY2021 for $495,500.00.

 

The Department of Transportation and Highways respectfully requests approval to amend a previously approved item. This previously approved items is a contract between the Department and Azteca Systems Inc., Sandy, Utah for Cityworks Software License and Maintenance. The cost has been reduced to $1,302,599.00 with annual fiscal impacts to FY2021 of $417,599.00, FY2022 of $427,000.00, and FY2023 of $458,000.00.

 

While the scope of work remains unchanged, the current hosting environment, an on-premises server, will continue to be used up until the time that the transition to the cloud can be executed. The previously approved contract did not include a provision for maintenance of the existing, on premises server prior to transition.  The reduction in contract cost is related to a reduction in the cloud hosting services.

end