title
PROPOSED COMPLETION OF CONSTRUCTION APPROVAL RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): MQ Construction, Chicago, Illinois
Action: Completion of Construction Approval Resolution
Good(s) or Service(s): Construction Services
Location of Project: 5th Avenue Bridge over I-294
Section: 20-B7120-00-BR
County Board District: 17
Contract Number: 1555-14475-SW-SWE18
Federal Project Number: N/A
Federal Job Number: N/A
Final Cost: $67,554.93
Percent Above or Below Construction Contract Bid Amount: 0.002% above the Construction Contract
Summary: The JOC improvement at 5th Avenue Bridge over I-294, consisted of guardrail removal and replacement, guardrail terminal sections, concrete pad with attenuator, traffic control and protection, site restoration and other necessary appurtenances has been completed under the supervision and to the satisfaction of the Superintendent.
The awarded contract amount of this project was $67,438.47 and the final construction cost is $67,554.93. The increase is attributed to the difference between the estimated and actual Gordian Group Services Fee.
end