File #: 24-0302    Version: 1 Name: GMA Construction Group, Chicago, Illinois
Type: Contract Amendment Status: Approved
File created: 11/27/2023 In control: Asset Management Committee
On agenda: 2/29/2024 Final action: 4/18/2024
Title: PROPOSED CONTRACT AMENDMENT Department(s): Department of Capital Planning and Policy Vendor: Griggs, Mitchell & Alma of IL, LLC d/b/a GMA Construction Group, Chicago, Illinois Request: Authorization for the Chief Procurement Officer to extend and increase contract Good(s) or Service(s): Construction Manager at Risk Services Original Contract Period: 10/1/2022 - 9/30/2024 Proposed Amendment Type: Extension and Increase Proposed Contract Period: Extension period 10/1/2024 - 12/31/2026 Total Current Contract Amount Authority: $24,200,000.00 Original Approval (Board or Procurement): Board, 9/22/2022 Increase Requested: $21,500,000.00 Previous Board Increase(s): N/A Previous Chief Procurement Officer Increase(s): N/A Previous Board Renewals: N/A Previous Chief Procurement Officer Renewals: N/A Previous Board Extension(s): N/A Previous Chief Procurement Officer Extension(s): N/A Potential Fiscal Impact: FY 2024, $5,750,000.00; FY 2025, $11,000,000.00...
Indexes: EARL MANNING, Director, Office of Capital Planning and Policy

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Department of Capital Planning and Policy 

 

Vendor:  Griggs, Mitchell & Alma of IL, LLC d/b/a GMA Construction Group, Chicago, Illinois

 

Request: Authorization for the Chief Procurement Officer to extend and increase contract 

 

Good(s) or Service(s):  Construction Manager at Risk Services 

 

Original Contract Period: 10/1/2022 - 9/30/2024

 

Proposed Amendment Type: Extension and Increase 

 

Proposed Contract Period:  Extension period 10/1/2024 - 12/31/2026

 

Total Current Contract Amount Authority:  $24,200,000.00

 

Original Approval (Board or Procurement):  Board, 9/22/2022

 

Increase Requested:  $21,500,000.00

 

Previous Board Increase(s):  N/A

 

Previous Chief Procurement Officer Increase(s): N/A

 

Previous Board Renewals:  N/A

 

Previous Chief Procurement Officer Renewals:  N/A

 

Previous Board Extension(s): N/A 

 

Previous Chief Procurement Officer Extension(s): N/A 

 

Potential Fiscal Impact:  FY 2024, $5,750,000.00; FY 2025, $11,000,000.00; FY 2026: $5,750,000.00

 

Accounts: 11569.1031.11190.560107.560108.00000.00000 Capital Improvement Program

 

Contract Number(s):  2123-18696

 

Concurrences:

The vendor has met the Minority- and Women-owned Business Enterprise Ordinance Via: Direct Participation. The prime vendor is a certified MBE.

 

The Chief Procurement Officer concurs.

 

Summary:  This contract amendment includes the addition of Preconstruction Services, General Conditions, and an Upper Limit for Guaranteed Maximum Price (GMP) Construction budget for floors 1 and 2 scope and extends the contract end date to allow sufficient time for construction completion.

 

The vendor was selected pursuant to a publicly advertised RFQ process in accordance with the Cook County Procurement Code.  GMA Construction Group was selected as the most qualified firm. As indicated in Board-Approved Item 22-4208, DCPP has developed a Guaranteed Maximum Price (GMP) not to exceed $21.5 million. 

end