File #: 24-3067    Version: 1 Name: Contract Amendment for Pavement Preservation and Rehabilitation Program – South 2022 –Co. number 2311-12020
Type: Contract Amendment (Highway) Status: Approved
File created: 5/7/2024 In control: Transportation Committee
On agenda: 9/19/2024 Final action: 10/24/2024
Title: PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS) Department(s): Transportation and Highways Vendor: Gallagher Asphalt / K-Five Construction Corp. JV, Thornton, Illinois Request: Authorization for the Chief Procurement Officer to increase contract Good(s) or Service(s): Construction Service Location: German Church Road - County Line Road to Wolf Road, Wolf Road - 131st Street to McCarthy Road Flossmoor Road - Ridgeland Ave to Kedzie Avenue Vollmer Road - Western Ave. to Dixie Highway Cottage Grove Ave. - Glenwood Lansing Road to 183rd Street Glenwood Lansing Road - East of IL-394 to West of Burnham Avenue Cottage Grove Ave. - Sauk Trail to 17th Street County Board District(s): 4, 5, 6, 17 Original Contract Period: 5/11/2023 - 12/31/2026 Section: 22-PRPS1-00-PV Proposed Contract Period Extension: N/A Section: N/A Total Current Contract Amount Authority: $14,196,889.90 Original Board Approval: 4/27/2023, $14,196,889.90 Previous Board Increase(s...
Indexes: JENNIFER (SIS) KILLEN, Superintendent, Department of Transportation and Highways
title
PROPOSED CONTRACT AMENDMENT (TRANSPORTATION AND HIGHWAYS)

Department(s): Transportation and Highways

Vendor: Gallagher Asphalt / K-Five Construction Corp. JV, Thornton, Illinois

Request: Authorization for the Chief Procurement Officer to increase contract

Good(s) or Service(s): Construction Service

Location:
German Church Road - County Line Road to Wolf Road,
Wolf Road - 131st Street to McCarthy Road
Flossmoor Road - Ridgeland Ave to Kedzie Avenue
Vollmer Road - Western Ave. to Dixie Highway
Cottage Grove Ave. - Glenwood Lansing Road to 183rd Street
Glenwood Lansing Road - East of IL-394 to West of Burnham Avenue
Cottage Grove Ave. - Sauk Trail to 17th Street

County Board District(s): 4, 5, 6, 17

Original Contract Period: 5/11/2023 - 12/31/2026

Section: 22-PRPS1-00-PV

Proposed Contract Period Extension: N/A

Section: N/A

Total Current Contract Amount Authority: $14,196,889.90

Original Board Approval: 4/27/2023, $14,196,889.90

Previous Board Increase(s) or Extension(s): N/A

Previous Chief Procurement Officer Increase(s) or Extension(s): N/A

This Increase Requested: $230,362.60

Potential Fiscal Impact: FY 2024 $230,362.60

Accounts: Rebuild Illinois: 11300.1500.29152.560019

Contract Number(s): 2311-12020

IDOT Contract Number(s): N/A

Federal Project Number(s): N/A

Federal Job Number(s): N/A

Concurrences:
The vendor has met the Minority- and Women-owned Business Enterprise Ordinance via: Direct participation and partial MWBE waiver.

The Chief Procurement Officer concurs.

Summary: The Department of Transportation and Highways respectfully requests approval of the proposed contract amendment between the County and Gallagher Asphalt / K-Five Construction Corp. Joint Venture, Thornton, Illinois.

This contract was approved by the Cook County Board on April 27, 2023, for Pavement Preservation and Rehabilitation Program - South 2022 located within the Cook County Board District 4, 5, 6, 17 in accordance ...