15-1550
| 1 | | | Committee Minutes | COMMITTEE MINUTES
Approval of the minutes from the meeting of 1/21/2015 | recommend for approval | Pass |
Action details
|
Video
|
15-1039
| 1 | | 108th Sup 95-W7510-01-FP | Supplemental Improvement Resolution (Highway) | PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Project Type: Motor Fuel Tax Project Supplemental
Request: Refer to the Committee of Roads and Bridges
Project: This improvement, as proposed, included the removal of the existing bituminous pavement and reconstruction in kind, the addition of bituminous shoulders, drainage additions and adjustments, driveway reconstruction, guardrail removal and replacement, landscaping, signing, pavement marking, engineering, and other necessary highway appurtenances.
Location: 108th Avenue, 153rd Street to 143rd Street in the Village of Orland Park.
Section: 95-W7510-01-FP
County Board District: 17
Centerline Mileage: 1.27
Fiscal Impact: $995,000.00
Accounts: Motor Fuel Tax Fund: (600 - 585 Account)
Board Approved Date and Amount: 4/5/1995, $2,300,000.00
Increased Amount: $995,000.00
Total Adjusted Amount: $3,295,000.00
Summary: The Department of Transportation and Highways respectfully submits for adoptio | recommend for approval | Pass |
Action details
|
Video
|
15-1040
| 1 | | Sup Imp Res Cottage Grove 98-W5812-02-PV | Supplemental Improvement Resolution (Highway) | PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Project Type: Motor Fuel Tax Project Supplemental Improvement Resolution
Request: Refer to the Committee of Roads and Bridges
Project: Reconstruction of Cottage Grove Avenue between Lincoln Avenue and 142nd Street with Hot Mix Asphalt (HMA); full depth concrete pavement patching between 142nd Street and the Indiana Harbor Belt (IHB) Railroad; bituminous reconstruction to three-lanes between the IHB Railroad and 138th Street including grade crossing renewal, curb and gutter, an enclosed drainage system, pavement marking, signing, landscaping and engineering and other necessary highway appurtenances.
Location: Cottage Grove Avenue, Lincoln Avenue to 138th Street in the Village of Dolton
Section: 98-W5812-03-PV
County Board District: 6
Centerline Mileage: 0.91
Fiscal Impact: $4,625,000.00
Accounts: Motor Fuel Tax Fund (600-585 Account)
Board Approved Date and Amount: 6/8/1999, $1,500,000.00
Increased Amou | recommend for approval | Pass |
Action details
|
Not available
|
15-1041
| 1 | | 123rd Street 01-B7528-05-PV | Supplemental Improvement Resolution (Highway) | PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Project Type: Motor Fuel Tax Project Supplemental Improvement
Request: Refer to the Committee of Roads and Bridges
Project: This improvement, as proposed, consisted of pavement reconstruction with bituminous materials, installation of an enclosed drainage system, continuous left turn lane, curb and gutter, culvert replacement, traffic signal installation, railroad grade crossing renewal, right-of-way acquisition, pavement markings, traffic protection, landscaping, consultant design with review by County Forces, and construction engineering.
Location: 123rd Street, Cicero Avenue to Kedzie Avenue in the Village of Alsip.
Section: Section: 01-B7528-05-PV
County Board District: 6
Centerline Mileage: 2.25
Fiscal Impact: $3,525,000.00
Accounts: Motor Fuel Tax Fund: (600-585 Account)
Board Approved Date and Amount: 5/15/2001 $9,000,000.00
Increased Amount: $3,525,000.00
Total Adjusted Amount: $12,525,000.00
| recommend for approval | Pass |
Action details
|
Not available
|
|