| 1 | | | Committee Minutes | COMMITTEE MINUTES
Approval of the minutes from the meeting of 2/10/2015 | recommend for approval | Pass |
Action details
|
Video
|
15-0973
| 1 | | C and P Narrag | Change in Plans and Extra Work (Highway) | PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): A Lamp Concrete Contractors Inc., in the Village of Schaumburg, Illinois
Action: Approval of change in plans and extra work by the Board upon recommendation of the Committee on Roads and Bridges
Section: Section: 08-W3719-04-FP
Contract Number(s): N/A
IDOT Contract Number(s): N/A
Federal Project Number(s): N/A
Federal Job Number(s): N/A
Location: Narragansett Avenue-87th Street to 79th Street in the Village of Burbank
Board District: 11
Good(s) or Service(s): Change in Plans Adjustment of Quantities. This change represents the difference between the estimated quantities and actual field quantities of work performed with additional quantities required for protective coat, hot mix asphalt binder course, hot mix surface course and concrete drives, per field conditions.
Fiscal Impact: $21,114.55 increase
Accounts: Motor Fuel Tax Fund (600-600 Account)
Summary: 6/14/2011, your honorable Bo | recommend for approval | Pass |
Action details
|
Video
|
15-0974
| 1 | | C and Plans Arlington Hts | Change in Plans and Extra Work (Highway) | PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Greco Contractors, Inc. Des Plaines, Illinois
Action: Approval of change in plans and extra work by the Board upon recommendation of the Committee of Roads and Bridges
Section: 09-V6946-03-RP
Contract Number(s): N/A
IDOT Contract Number(s): N/A
Federal Project Number(s): N/A
Federal Job Number(s): N/A
Location: Arlington Heights Road, University Drive to Lake Cook Road in the Villages of Arlington Heights and Buffalo Grove.
Board District: 14
Good(s) or Service(s): A new item was added for temporary speed limit signs.
Fiscal Impact: $2,787.20 decrease
Accounts: Motor Fuel Tax Fund (600-600 Account)
Summary: On 12/14/2010, your honorable Body awarded a contract to Greco Contractors, Inc., Illinois for the aforesaid improvement to be completed in accordance with the plans and specifications.
The quantities as shown on the contract documents were estimated for bidding purposes only. This change rep | recommend for approval | Pass |
Action details
|
Not available
|
15-0975
| 1 | | C & P 171st | Change in Plans and Extra Work (Highway) | PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Albin Carlson & Company, the Village of Addison, Illinois
Action: Approval of change in plans and extra work by the Board upon the recommendation of the Committee on Roads and Bridges
Section: 04-B8431-08-PV
Contract Number(s): 10212
IDOT Contract Number(s): C-91-278-04
Federal Project Number(s): CMM-HPD-M8003-(427)
Federal Job Number(s): N/A
Location: 171st Street, Wood Street to Ashland Avenue in the Villages of East Hazel Crest, Hazel Crest and the City of Harvey.
Board District: 5, 6
Good(s) or Service(s): This change represents the difference between the estimated quantities and actual field quantities of work performed with savings in earth excavation, aggregate base course TY-B 10 in., ductile iron watermain, 30 in. steel sleeve open cut, conduit attached to structures, and credit share of railing reinforcement repair. New items were added for credit share of railing reinforcement repair, inductive loop | recommend for approval | Pass |
Action details
|
Not available
|
15-0976
| 1 | | C & P Lake Cook Road | Change in Plans and Extra Work (Highway) | PROPOSED CHANGE IN PLANS AND EXTRA WORK (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Other Part(ies): Capitol Cement Company, Inc. in the City of Chicago, Illinois
Action: Approval of change in plans and extra work by the Board upon the recommendation of the Committee of Roads and Bridges
Section: 01-A5020-02-RP
Contract Number(s): N/A
IDOT Contract Number(s): N/A
Federal Project Number(s): N/A
Federal Job Number(s): N/A
Location: Lake Cook Road, East of Wilmot Road to Pfingsten Road in the Village of Deerfield
Board District: 14
Good(s) or Service(s): Adjustment of Quantities and New Items were required for relocating fire hydrant, locating MCI cable, extra work to install water main in conflict with ComEd ducts and retaining wall, speed bump test, additional block retaining wall, variable height b-curb, additional concrete median restoration, pressure connection, extra work to mill and replace for asphalt placement at Pine Street, cover concrete work in cold weather and premium time acceleration.
Fiscal Impa | recommend for approval | Pass |
Action details
|
Not available
|
15-1350
| 1 | | Archer Road 04-B5115-02-RS | Supplemental Improvement Resolution (Highway) | PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Project Type: Motor Fuel Tax Project Supplemental Improvement Resolution
Request: Approval of a supplemental improvement resolution appropriating additional funds upon the recommendation of the Committee on Roads and Bridges
Project: Pavement widening, milling and resurfacing of the existing pavement, channelization, full depth patching, drainage improvements, right-of-way, traffic protection, landscaping, pavement marking, engineering and other necessary highway appurtenances along 131st Street from Archer Avenue to Wolf Road in the Village of Lemont.
Location: 131st Street, Archer Avenue to Wolf Road in the Village of Lemont
Section: Section: 04-B5115-02-RS
County Board District: 17
Centerline Mileage: 5.01
Fiscal Impact: $115,000.00
Accounts: Motor Fuel Tax Fund (600-585 Account)
Board Approved Date and Amount: 11/6/2004, $4,800,000.00
Increased Amount: $115,000.00
Total Adjusted Amount: $4,915,0 | recommend for approval | Pass |
Action details
|
Video
|
15-1351
| 1 | | Cottage Grove 05-W5906-03-FP | Supplemental Improvement Resolution (Highway) | PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Project Type: Motor Fuel Tax Project Supplemental Improvement Resolution
Request: Approval of a supplemental improvement resolution appropriating additional funds upon recommendation of the Committee of Roads and Bridges
Project: Milling, patching, widening and/or surfacing of the existing pavement, etc.
Location: Cottage Grove Avenue, Glenwood-Lansing Road to Thornton-Lansing Road in the Villages of Glenwood and Thornton.
Section: 05-W5906-03-FP
County Board District: 6
Centerline Mileage: 2.21
Fiscal Impact: $303,000.00
Accounts: Motor Fuel Tax Fund (600-585 Account)
Board Approved Date and Amount: 11/1/2005, $2,475,000.00
Increased Amount: $303,000.00
Total Adjusted Amount: $2,778,000.00
Summary: Additional funding was needed due to expansion of the project to include guardrail removal and replacement up to current standards, tree removal and replacement and related items. The project w | recommend for approval | Pass |
Action details
|
Not available
|
15-1352
| 1 | | Wolf Road 96-W2312-02-FP | Supplemental Improvement Resolution (Highway) | PROPOSED SUPPLEMENTAL IMPROVEMENT RESOLUTION (TRANSPORTATION AND HIGHWAYS)
Department: Transportation and Highways
Project Type: Motor Fuel Tax Project Supplemental Improvement
Request: Approval of a supplemental improvement resolution appropriating additional funds upon recommendation of the Committee of Roads and Bridges
Project: Bituminous pavement reconstruction and widening, culvert replacement, guardrail removal and replacement, landscaping, pavement marking, signing, engineering and other necessary highway appurtenances along Wolfe Road, 143rd Street to 123rd Street in the Village of Palos Park.
Location: Wolfe Road, 143rd Street to 123rd Street in the Village of Palos Park
Section: 96-W2312-02-FP
County Board District: 17
Centerline Mileage: N/A
Fiscal Impact: $730,000.00
Accounts: Motor Fuel Tax Fund (600 585 Account)
Board Approved Date and Amount: 6/18/1996 $1,500,000.00
Increased Amount: $730,000.00
Total Adjusted Amount: $2,230,000.00
Summary: Additional funding was needed due to expansion of the i | recommend for approval | Pass |